Resolved that – (i) authority be granted for the Executive Director (Regeneration) to accept the £17,106 Land Reclamation Grant, through the City Centre Environmental Improvement Programme, to finance the project. This will bring the total grant to £237,106; (ii) the Manager of the City Centre Projects Team, be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant (this includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises); (iii) subject to the final works contract not exceeding £ 217,106 and remaining professional fees not exceeding £20,000, authority be granted to commit the additional Land Reclamation Grant of £17,106 (total of £237,106) to the Berkley Place contract; and (iv) the City Council’s capital programme be re-profiled to reflect expenditure on this project of £88,000 during 2004/05, £149,106 in 2005/6, and that authority be given to commit this expenditure through the City Centre EIP. GI1/4
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This summary relates to the delivery of a new area of public space named Berkley Place (formerly Upper Parliament Street / Catherine Street). This scheme aims to take advantage of the recent closure of a section of Berkley Street by delivering an area of high quality public open space. The scheme is designed to benefit both local residents and visitors to Liverpool through the creation of a high quality useable space for local people, and a recognisable gateway to and from Liverpool City Centre.
The delivery of the scheme has been previously approved by Executive Board on the 22nd of December 2004 (Upper Parliament Street/Catherine Street public open space project, REG/50). Since the submission of the report the tenders have been returned, and have come in higher than anticipated. The costs previously reported to the Executive Board were based on the estimated costs, with the funding levels also based on these costs. There are several reasons for these increased costs, including unexpected rises in some material costs, and rises in labour costs across Merseyside. The purpose of this summary is to seek approval to accept additional funding to enable delivery of the project, and to seek approval to commit the additional funding.
The scheme will be 100% funded through the City Centre Environmental Improvement Programme (EIP), which is joint funded by the North West Development Agency (NWDA) and English Partnerships (EP). There will be no additional capital cost to the City Council. The maintenance of the space will be the responsibility of the City Council as the space will remain adopted highway. Executive Member/Director recommendation (Cllr Millea, Cllr Turner / Charlie Parker)
It is recommended that, in relation to the Berkley Place public open space project:
(i) authority be given to the Executive Director (Regeneration) to accept the £17,106 Land Reclamation Grant, through the City Centre Environmental Improvement Programme, to finance the project. This will bring the total grant to £237,106;
(ii) the Manager of the City Centre Projects Team, will be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant (this includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises);
(iii) subject to the final works contract not exceeding £ 217,106 and remaining professional fees not exceeding £20,000, authority be given to commit the additional Land Reclamation Grant of £17,106 (total of £237,106) to the Berkley Place contract; and
(iv) the City Council’s capital programme be re-profiled to reflect expenditure on this project of £88,000 during 2004/05, £149,106 in 2005/6, and that authority be given to commit this expenditure through the City Centre EIP.
Key Decision? No
Forward Plan No
Implementation effective from
29 March 2005
Timescale for action
The project has been identified within the City Centre EIP Performance Plan 2004/5. Works are due to begin in February 2005, and are due to be completed by May 2005. Reason(s) for Recommendation
The recommendation is required so that the additional funding can be expended on the project. A start on site will be made during February to enable necessary spend during 2004/5. Adjustments to the contract will be made upon the approval to commit the additional expenditure.
Alternative options to be considered
a) Reduce the contract sum
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.