Resolved that – (i) authority be granted for the Executive Director (Regeneration) to accept capital grants totalling £116,000 (£70,000 NWDA, £46,000 SRB). The City Council will accept the role of accountable body and ensure that the grant is administered properly; (ii) the City Centre Projects Team Leader to be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises. (iii) authority be granted for the Executive Director (Regeneration) to issue grant offer letters to the respective building owners included within Phase 1 additional lighting projects and thereby commit expenditure of £104,000; (iv) authority be granted for the Executive Director (Regeneration) to extend the appointment of Rose Project Services by the commitment of an additional £12,000 to enable the project management of the Phase 1 additional lighting projects; and (v) the City Council’s 2004/05 capital programme be adjusted to reflect additional expenditure on the City Centre Feature Lighting Phase 1 project totalling £116,000 which will be wholly funded by grant. REG/75
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Phase 1 of City Centre Feature Programme has been successful in lighting 28 buildings prior to programme completion in December 2004.
The programme was developed from the lighting implementation plan for the City Centre which was commissioned by the City Council in partnership with Liverpool Vision. This focussed on the architectural lighting of buildings with the view that a high quality lighting scheme would improve Liverpool’s image by: i. increasing the desirability of City Centre Living ii. increasing the desirability of City Centre employment iii. encouraging night time economic activity
Among the buildings lit in Phase 1 are the Metropolitan and Liverpool Cathedrals, the three Graces, Liverpool Town Hall and several buildings in the Cultural Quarter. Interest among building owners has been such that several further schemes were developed to design stage, but were not implemented due to a lack of available public sector funding.
Four of these projects, Municipal Building, North Western Hall, Albert Dock and St John’s Tower have been developed to tender stage and would be able to be implemented almost immediately. Grants would therefore be payable to building owners to enable feature lighting works to be undertaken.
Sufficient additional public sector funding has been identified by NWDA and SRB to enable these projects to proceed on condition that they are financially complete by 31 March 2005.
Executive Member/Director recommendation (Councillors Peter Millea and Keith Turner/Charlie Parker):
That: -
i). authority be given to the Executive Director for Regeneration to accept capital grants totalling £116,000 (£70,000 NWDA, £46,000 SRB). The City Council will accept the role of accountable body and ensure that the grant is administered properly;
ii). the City Centre Projects Team Leader to be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises.
iii). authority be given to the Executive Director for Regeneration to issue grant offer letters to the respective building owners included within Phase 1 additional lighting projects and thereby commit expenditure of £104,000.
iv). authority be given to the Executive Director for Regeneration to extend the appointment of Rose Project Services by the commitment of an additional £12,000 to enable the project management of the Phase 1 additional lighting projects.
v). the City Council’s 2004/05 capital programme be adjusted to reflect additional expenditure on the City Centre Feature Lighting Phase 1 project totalling £116,000 which will be wholly funded by grant.
Key Decision
Yes
Forward Plan
No – appropriate notices will be published in accordance with the constitution Implementation effective from: 29 March 2005
Timescale for action:
Grant agreements will be issued to building owners once Executive Board approval has been gained.
Projects were designed and tendered during Phase 1 of the programme, and work would commence immediately that signed grant agreements have been returned.
All work will be complete by 31 March 2005.
Reason(s) for Recommendation:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.