Resolved that – (i) the City Council enters into a development agreement with Urban Splash Group Ltd. regarding the redevelopment of the Great George Street/St. James Street area on the terms set out in the report. submitted; and (ii) the City Council resolves to use its Compulsory Purchase powers to assemble the site for redevelopment if required. REG/76
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1.1The Executive Board of 14th November 2003 approved the appointment of Urban Splash as preferred developer partner for the redevelopment of the Great George Street/St. James Street area.
1.2Appropriate City Council officers were authorised to negotiate a development agreement with the preferred partner and to report back the heads of terms for that agreement once it had been finalised.
2. Housing issues
2.1The properties involved mainly comprise three storey blocks of flats. Authority has been given to decant the tenants from all of the flats and demolish them as they fall vacant.
2.2There are currently 186 units affected by the redevelopment proposals of which 69 units have already been demolished. There are 60 tenants left to be rehoused of which 7 have accepted new units within the Arts Village development. A further 6 units to rent will be available within the new Maritime development in Nelson Street. There are also 6 owner occupiers whose properties need to be acquired.
2.3The majority of the remaining residents have aspirations to remain in the area. The vacation of the remaining units proposed for redevelopment will therefore need to be achieved by a combination of rehousing in existing stock in the area and some new build social housing within the scheme.
2.4To help produce a mixed tenure scheme the Council supported Maritime Housing Association in achieving grant funding from the Housing Corporation to develop 36 apartments for shared ownership. This funding had to be committed by the end of 2005/6 and because of delays in the delivery of the scheme this will no longer be achievable. The Housing Corporation have advised that they will look favourably on a new application for 2006/7.
2.5Although the above accommodation will assist with the rehousing there will still be a need for further units to complete the process. As part of the negotiations with Urban Splash it has been agreed that they provide 15 units for rent. It is proposed that the majority of the cost of these units, and part of the cost of the shared ownership units, will be funded out of the land value. The balance will be funded by Maritime.
3. The development agreement
3.1It has taken longer than expected to agree terms with Urban Splash but heads of terms have now been provisionally agreed in a form that can be recommended for approval.
3.2The agreement will provide for 150 year leases to be granted in respect of each phase of the development as vacant possession of that phase is secured and other conditions are satisfied. The leases will be on full repairing and insuring terms with a rental of one peppercorn per annum.
3.3There will be 3 phases as shown on the attached plan.
• Phase 1 will comprise c. 300 units including the 36 apartments for shared ownership and 15 houses to rent • Phase 2 will comprise c. 200 units including 16 units to rent • Phase 3 will comprise c. 100 units.
3.4Phase 1 includes three properties that are currently held on lease from the City Council. Terms have been agreed to acquire 121-123 St. James Street. Negotiations are to be progressed to obtain possession of the adjoining former petrol station site. It has not proved possible to negotiate the purchase of the third property, 109-111 St. James Street. It has been agreed with Urban Splash that they will acquire this property and include it in the scheme – this is another cost to be funded out of the residual land value.
3.5Phase 3 will include the site on the corner of Great George Street and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.