Resolved that – (i) authority be granted for the Executive Director (Regeneration)to accept an ERDF grant totalling £7,660,000. The City Council will thereby accept the role of the Accountable Body and ensure that the grant is administered appropriately; (ii) the Highways Manager be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability is likely to rise; (iii) subject to recommendation (v) expenditure on this project apart from design and tender costs be only incurred after the receipt of confirmation of funding from all the relevant organisations/bodies upon which this project relies for income and the finalisation of all other relevant documents; (iv) the City Council’s Capital Programme be adjusted, on receipt of a formal approval letter for the ERDF grant, to reflect expenditure on the Edge Lane project totalling £8,488,000, phased over the financial years 2005/06, 2006/07 and 2007/08 with a commitment to provide Transport Service general resources of £400,000 in 2006/07 and £350,000 in 2007/08; and (v) approval be given to incur scheme expenditure on receipt of an acceptable ERDF grant offer letter.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
I. To update the Executive Board as to the progress of the Edge Lane Improvements initiative.
II. To advise the Executive Members of and seek approval for, various management mechanisms associated with the project.
III. To seek permission for the City Council to be given approval to accept the ERDF offer letter issued, amend the Capital Programme accordingly and commit the expenditure.
Executive Member/ Director recommendation: Cllr Peter Millea, Cllr Turner/Charlie Parker
It is recommended that:
(i) Authority be given to the Executive Director for Regeneration to accept an ERDF grant totalling £7,660,000. The City Council will thereby accept the role of the Accountable Body and ensure that the grant is administered appropriately
(ii) The Highways Manager be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability is likely to rise.
(iii) Subject to recommendation (v) expenditure on this project (apart from design and tender costs) is only to be incurred after the receipt of confirmation of funding from all the relevant organisations/bodies upon which this project relies for income and the finalisation of all other relevant documents.
(iv) The City Council’s Capital Programme be adjusted, on receipt of a formal approval letter for the ERDF grant, to reflect expenditure on the Edge Lane project totalling £8,488,000, phased over the financial years 2005/06, 2006/07 and 2007/08 with a commitment to provide Transport Service general resources of £400,000 in 2006/07 and £350,000 in 2007/08
(v) Approval be given to incur scheme expenditure on receipt of an acceptable ERDF grant offer letter.
Key Decision?
Yes
Forward Plan/3 days notice/special urgency:
3 days notice
Implementation effective from:
Immediately
Timescale for action: Funding:
March 05 Detailed ERDF funding bid submitted June 05 Funding appraisal complete (anticipated) June 05 Offer letters issued (anticipated)
Project Programme:
May 2005 LCC Checking/Approvals complete for Edge Lane Drive June 2005 Complete Tender Documentation for Edge Lane Drive/Central July 2005 Tender selection and contract let August 2005 Work commences on Edge Lane Central Early 2007 Work commences on Edge Lane Drive Reason(s) for Recommendation:
(1) To inform and update Members on the progress of the scheme known as Eastern Approaches – Edge Lane Improvements.
(2) To advise Members of and seek approval for various management and maintenance mechanisms associated with the project.
Alternative options to be considered:
In considering the potential transport options a Preliminary Qualitative Strategic Appraisal was carried out that reviewed 9 options: - ‘Dual Carriageway without Tram’ - ‘Dual Carriageway with Tram’ - ‘Dual Carriageway with parking’ - ‘Single Carriageway without Tram’ (where single carriageway represents a 2 lane highway in each direction without a central reservation); - ‘Single Carriageway with Tram’; - ‘Single Carriageway with parking’; - ‘Do Nothing’ - Motorway; and, - Composite scheme.
Consultation
The following have been consulted:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.