Resolved
Resolved that Neslo be confirmed as the main contractor for delivery of Edge Hill Customer Focus Centre.
Executive Board decided this item on Friday 5 August 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that Neslo be confirmed as the main contractor for delivery of Edge Hill Customer Focus Centre.
Edge Hill Customer Focus Centre (previously known as Wavertree Customer Focus Centre) report was agreed in September 2004 (RES/24) and January 2005 RES/56 with a pre-tendered estimated project cost of £1.96 million. Following the tender process project costs including additional works eg. Structural bracing, heating system, CCTV and Car Parking etc have now been confirmed as 1.84 million including preliminaries and consultancy fees.
This development will be the fourth Customer Focus Centre. Currently based on site is the Chatsworth former Housing Office, Wavertree Road Supported Living and The Family Advisory Service building.
These buildings, will be refurbished to full DDA standards with an open plan design, shared meeting/interview facilities with the potential to house up to 400 staff. Currently this site houses just 146 staff.
The three buildings would be extensively refurbished to provide a ‘back office’ facility for mixed service provision promoting joined up working to the benefit of the customer. These buildings have significant maintenance and security issues and currently fail DDA standards (with all the associated cost implications, they also provide a poor working environment for staff and this will be address as part of the refurbishment works. 2. Proposal
This project has now been through the official tendering process (out to the six contractors successful at pre-qualification stage) and as a result of the final evaluation it is proposed to award the tender to Neslo with the lowest tender bid) at a total cost of £1.84 million. The refurbishment including the additional works identified will be completed within 26 weeks of contractor starting on site (anticipated February 06).
Executive Member/ Executive Director (Councillor Keith Turner / David McElhinney)
To confirm Neslo as the main contractor for delivery of Edge Hill Customer Focus Centre.
Key Decision?
Yes .
Forward Plan/5 days notice/special urgency
Yes
Implementation effective from
12 August 2005
Timescale for action
Officers have commenced procurement process and investigations to refurbish this building in a manner which meets the requirements of contract Standing Orders and Financial Regulations.
Reason(s) for Recommendation
This development contributes to the accommodation strategy allowing us to rationalise buildings leased and owned and comply with DDA obligations
The three existing buildings on the site will be temporarily vacated by existing staff to Brougham Terrace CFC. This will then enable refurbishment work to commence. Approximately 400 Staff are scheduled to be relocated to the site following completion of refurbishment. Alternative options considered
All existing accommodation across all districts of Liverpool were considered for development as a Customer Contact Site/ Customer Focus Centre. Geographical limitations and height/size restrictions were applied in final selection.
Customers, staff and trade union consultation will continue and is included in the project plan for each customer focus centre (on a project by project basis).
Project costs will be met by existing capital and support funding for 2005/06.
Revenue Implications
None as a result of this report.
The building improvement programme will incorporate improved accessibility for all disabled people. Access to work assessments and staff diversity requirements will be accounted for in terms of building and IT provision.
Corporate strategy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Edge Hill CFC contractor (RES/25)Report | 5 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.