Resolved that – (i) approval be given to amend the approved 2005/06 Transportation Capital Programme to reflect the proposed expenditure shown in Appendices 1 and 2 submitted; (ii) the contract sum for the A565 Atlantic Avenue (Phase 4) be amended from £1,230,425.65 to £1,485,997.32; (iii) the HMRI allocation for 2005/06 for the Park Road/Mill St scheme be reduced from £2.140m to £2.000m; and (iv) approval be given to commit expenditure to schemes requiring financing by general resources of £12.856m, grant of £19.365m and private contributions of £3.527m as detailed in the Financial Implications and Appendices 1 and 2 submitted.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This report seeks to obtain approval for the amended 2005/06 Transportation Capital Programme as detailed below and in the attached Appendices 1, 2 and 3.
THE TRANSPORTATION CAPITAL PROGRAMME 2005/06
1. The proposed Transportation Capital Programme (TCP) for 2005/06 focuses on the delivery of: • Corporate objectives of the Council. • The Regeneration Portfolios’ Business Plan. • The Local Transport Plan (LTP). • Key priorities of partner organisations (LLDC, Liverpool Vision, Merseytravel etc).
2. The aim of the LTP is to develop a fully integrated and sustainable transport network for Merseyside which supports economic, social and environmental regeneration and ensures good access for all in the community.
3. The plan has the following core objectives: • Well serviced, safe and sustainable neighbourhoods with optimum local accountability and influence over service management • A healthy environment for all who live in, work or visit the city and an effective and accessible transport system
4. To achieve these objectives several strategies have been developed within the LTP. These include: • Identifying transport mode hierarchies in each of the ‘Corridors and Centres’ across Merseyside to ensure that the right solutions are targeted to the right locations. • Developing walking and cycling networks linking the ‘Pathway Areas’ with the Strategic Investment Areas (SIA’s) and other residential areas with key destinations such as schools, local shops and amenities, employment sites and health facilities. • Improving Public Transport services and facilities in order to maximise accessibility for all. • Managing freight movements from the docks and other key industrial/manufacturing areas to support the economy and reduce the impact of HGVs on adjoining communities. • Encouraging the use of more sustainable modes of transport and promoting ‘TravelWise’ behaviour by raising the awareness of advantages of sustainable travel for both individuals and society as a whole. • Reducing the need to travel by car through locating land uses to maximise the use of more sustainable transport modes. • Improving road safety by reducing speeds and conflicts through both physical methods and education, training and publicity programmes. • Ensuring accessibility for all by meeting the requirements of the Disability Discrimination Act, improving public transport services and providing community transport opportunities. • Maintaining the network to ensure safety and to gain the maximum benefit from the existing infrastructure.
Executive Director recommendation: Charlie Parker
That :- 1. approval be given to amend the approved 2005/06 Transportation Capital Programme to reflect the proposed expenditure shown in the attached Appendices 1 and 2; 2. the contract sum for the A565 Atlantic Avenue (Phase 4) be amended from £1,230,425.65 to £1,485,997.32; 3. the HMRI allocation for 2005/06 for the Park Road/Mill St scheme be reduced from £2.140m to £2.000m. 4. approval be given to commit expenditure to schemes requiring financing by general resources of £12.856m, grant of £19.365m and private contributions of £3.527m as detailed in the Financial Implications and Appendices 1 and 2.
Key Decision?
Yes
• Forms part of the Council’s budget and policy framework. • Involves incurring expenditure over £250,000. • Decision affects more than one ward.
Forward Plan / 3 days notice / Special Urgency:
Forward Plan. Implementation effective from:
Immediate.
Timescale for Action:
It is essential that the programme is approved so that:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.