Resolved that - (i) the City Council dispose of sites 1a and 1b at Stonebridge Cross as shown on the plan submitted to David McLean Homes ( DMH ) subject to a premium of £7.0m and £4.0m respectively; (ii) the Council enter into a Preferred Developer Agreement and Building Agreements with DMH Limited on terms agreed by Liverpool Land Development Company in respect of the sites 1a and 1b in accordance with the terms set out in Appendix A submitted; (iii) the heads of expenditure as listed in the financial implications section of the report submitted be met from the capital receipts for site 1a and 1b and a further report be submitted, if appropriate, in respect of any additional expenditure which may need to be committed in connection with the development; (iv) the Council enter into an agreement with Cobalt Housing to provide a capital grant, funded from the capital receipt, to assist Cobalt Housing purchase, from DMH , 32 houses for social rent; (v) a further report be submitted on the funding arrangements to purchase the commercial interests at Shard Close; and (vi) DMH be granted an option to enter into a Preferred Development Agreement in respect of the land in phase 2 and the new Liverpool Visionwork with DMH , the Council and other stakeholders to work up a masterplan and report back to the Executive Board on the proposals for the site. CHS/42
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
To advise and seek approval to proposals negotiated by LLDC and the Council with David McLean Homes Limited (DMH) for the redevelopment of land at Stonebridge Lane and the East Lancashire Road.
Background
The Stonebridge Cross Regeneration Project comprises land in various ownerships with the major land owner being the City Council.
On behalf of the City Council and the various land-owning partners a consortium of Tesco and David McLeans was selected in 2002 by LLDC. The consortium’s proposals involved the development of a large food store together with ancillary retail units, new leisure facilities and approximately 300 new homes including a number of social rented homes.
However it subsequently became clear that the consortium’s proposals for a significantly sized food store as an anchor to the whole scheme was impossible for the Planning Authority and Government Office for the North West to support.
Consequently, it has been necessary to re-structure the approach and change the emphasis of the first phase of the project from being driven by retail to focus on the development of new homes.
A report was considered by the Executive Board on 13 April 2007 regarding proposals negotiated by LLDC with DMH for the development of the site. This report identified issues with the proposal as it then stood as:- a) the mix of housing in the light of the City’s housing objectives, particularly the number of flats and apartments
b) the best way of providing the synthetic sports pitches, as part of the Section 77 consent
c) uncertainty about the type, deliverability and sustainability of the phase 2 development and the risk of the scheme being called in on planning grounds by the Secretary of State
The Executive agreed that City Council should extend the exclusivity agreement with McLeans to allow discussion on these issues and a report to be brought back to the Executive Board.
The City has led further discussions with David McLeans on Phase 1 and this report sets out revised development proposal negotiated with McLeans.
Development Proposals
Phasing/delivery
The scheme is to be developed out in phases.
Phase 1 (which comprises sites 1a and 1b, as shown on the attached plans) will comprise predominantly of private housing, with a small number of social rented houses (32 in number). As part of the section 77 consent site 1b will include a five- aside football pitch facility which will be constructed in conjunction with the development on site 1a and before housing development commences on site 1b.
Work will start on site in respect of site 1a first, subject to planning permission being granted (see comments under section relating to Planning). Development of site 1b will be staggered and will commence after work had start on site 1a.
Phase 2 (as identified on the plan) would be delivered upon the completion of further site assembly work and is intended to comprise a mix of retail, commercial and community uses with the potential for further residential development, if appropriate. No start date has as yet been identified but it is anticipated the development can commence in parallel with the development on phase 1.
Residential Mix
The City has renegotiated the mix of size and type of property. Details of the previous mix and the revised mix are set out below.
Revised Mix (Sept. 2007) Original Mix (April 2007)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.