Resolved that – (i) Enabling Works Contracts be awarded to contractors under the Building Schools for the Future ( BSF ) Framework Contract up to a maximum value of £2,245,811 across the five schemes funded through the BSF capital grant; and (ii) in the event of scheme cancellation between enabling works and main contracts, the Children’s Services portfolio will cover the cost of abortive works through its current capital and revenue budgets. EDE/25
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
It is currently forecast that scheme construction contracts to deliver Liverpool’s Wave 2 of the Building Schools for the Future (BSF) project will start on site from September 2008.
In order to utilise both summer holiday periods and the Partnerships for Schools (PfS) Final Business Case (FBC) review periods prior to contract award, it is proposed that a series of Enabling Works packages on four out of the five Wave 2 schemes are awarded. The enabling works packages will include some pre-orders of materials (predominantly steelwork for the first 4-6 week period), to avoid lengthy material order periods at the beginning of construction.
This report seeks approval to award these enabling works contracts under the BSF Construction Framework Contract in advance of the main scheme contracts being approved and awarded.
Background Information:
In February 2007, the report CHS/04/07 approved the establishment of a design and build construction framework to deliver Liverpool’s Wave 2 Building Schools for the Future project. The report approved the appointment of Balfour Beatty, Morgan Ashurst (formerly Amec) and Norwest Holst to the framework.
Over the past 12 months, the designs of the five schemes in Wave 2 have been developed under this framework namely: 1. Alsop (through a design procurement with 2020 Liverpool and traditional contract arrangement with Morgan Ashurst). 2. West Derby / Ernest Cookson (design and build with Balfour Beatty). 3. King David (design and build with Norwest Holst). 4. Broughton Hall and Cardinal Heenan (design and build contract with Morgan Ashurst). 5. Gateacre / Hope (design and build with Balfour Beatty).
As a result of the detailed secondary review by Children’s Services in Autumn 2007, the Croxteth and New Heys schemes originally in Wave 2 were deferred to Wave 6. It is anticipated that a Strategy for Change document to commence the Wave 6 process will be submitted in early-summer 2008. Following development of the scheme design and contractual negotiations on the framework contract itself, all three contractors signed the framework contract in February 2008 (prior to specific scheme contracts for the construction of each scheme). The schemes are now in detail design stages and over the next 6 months the works will all be competitively procured and priced by the contractors prior to submitting an FBC for each scheme to PfS.
Following receipt of individual offer letters from PfS, the receipt of a Governing Body Agreement, a further report to the Executive Board and finally detailed planning permission, scheme contracts will be awarded to contractors to start construction from September 2008.
The current construction programme anticipated contract award and start on site dates as follows:
Alsop September 2008 Broughton Hall / Cardinal Heenan October 2008 West Derby / Ernest Cookson November 2008 Gateacre / Hope December 2008 King David January 2009
Enabling Works Packages
The reasons for the requirement to award enabling works contracts are as follows:
§ As referred to above, the construction programmes for the schemes all currently anticipate start on site dates after the 6-week 2008 summer holiday period. It is highly desirable from an operational and health and safety perspective that any demolition, diversion of services and set up of hoarding and site compound is carried out when there are fewer children on site. This is specifically in relation to both Alsop and Broughton Hall/Cardinal Heenan where starts on site dates follow shortly into the Autumn 2008 term.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.