Liverpool City Council
Executive Board, Friday 25 April 2008

Accepting the Housing Market Renewal Fund (HMRF) Grant from the Department of Communities & Local Government (CLG) for Liverpool and the Newheartlands pathfinder for the period 2008/11(NH/29)

Agreed Executive 1 paper

Executive Board agreed this item on Friday 25 April 2008. Below is the council's own wording, with the papers it was decided on.

Item222a

Resolved

Resolved that - (i) subject to the Executive Director (Regeneration) and the Acting City Solicitor agreeing the Deed of Variation to the existing ODPM (now CLG ) funding Agreement, and on the re ceipt of offer letters from CLG authority be granted to accept additional CLG grant of £ 152 million and be phased over the financial years 2008/09 (£54m), 2009/10 (£51m) and 2010/11 (£47m) towards the cost of the HMRI Implementation Programme on terms approved by the Executive Director (Regeneration) in consultation with the Acting City Solicitor and to affix the Council’s Seal to the necessary funding agreement ; (ii) approval be given to commit and spend up to £30.65 million in 2008/09. This involves a minimal risk to the authority until the HMRI Deed of Variation is agreed subject to Sefton and Wirral MBC who are progressing similar arrangements to spend at their own risk to ensure the momentum of the programme is maintained; (iii) the Divisional Manager for Regeneration Policy & Programmes to continue as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arise; and (iv) a further detailed report to be presented on Liverpool, Sefton and Wirral allocation and a three year financial plan detailing how costs will be allocated according to the CLG offer conditions for the City Council Expenditure. L&CS/22
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 7 pages

Executive summary

Purpose of report

The purpose of this report is to inform Executive Board of the recent announcement of further Housing Market Renewal Fund (HMRF) for the Merseyside Newheartlands Pathfinder programme and to secure permission to spend grant from the 1 April 2008 pending the receipt of a formal offer of grant from Communities and Local Government (CLG).

Background

In 2003 Liverpool City Council (LCC) accepted a total of £6.6M HMRF to address Housing Market issues across Merseyside. In February 2004 LCC accepted an additional £86M and agreed to continue to act as Grant Funded Authority (GFA) for the funding.

In 2006 CLG announced a further offer of grant funding of £97.7m for Newheartlands pathfinder over the two years of 2006-08. The grant was split £46.7m in 2006/07 and £51m in 2007/08.

In the autumn of 2007 Government Ministers announced that a total of around £1billion would be committed to the Housing Market Renewal Programme for the period 2008-11. Housing Minister Iain Wright confirmed on Thursday 28 February 2008 that NewHeartlands would be awarded a total of £152 million, divided as follows; £54m for 2008/09 and an indicative allocation (at this stage) of £51m for 2009/10 and £47m for 2010/11.While the allocation for 2008/9 is a firm commitment, years two and three are indicative and subject to a possible change of either plus or minus 10% depending on progress.

Approval is sought from Executive Board to accept the grant from CLG and commit to spend the additional grant aid in line with the NewHeartlands Business Plan (implementation Programme) agreed with CLG as follows:

Table 1 Funding Allocation 2008/11 2008/09 £54 million 2009/10 £51 million 2010/11 £47 million

Total £152 million

The majority of this allocation is capital as all Pathfinders are limited to a maximum of 10% revenue expenditure. An agreement has been reached between the participating Local Authorities and CLG what constitutes revenue expenditure.

Liverpool is the designated GFA through which all funding for the Newheartlands Pathfinder will flow. The HMRF allocation for 2008/09 is £54m which is £1m more than forecast within the Newheartlands Business Plan of £53m. The Newheartlands Board will have to decide how to divide out the extra £1m The HMRF forecast to be spent in Liverpool in 2008/9 is £30.65m. This is equal to that forecast within the Newheartlands Business Plan. This could increase slightly depending on the eventual share out of the extra £1m.

It is unlikely that the signing of the funding agreement (Deed of Variation) between CLG and LCC will take place before the start of the new financial year, 2008/09. To maintain the momentum of the programme Liverpool will be required to spend at risk in the absence of the funding agreement. That risk is considered to be low on the basis of the recent Government announcement confirming their support nationally for the HMR Scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Accepting the Housing Market Renewal Fund (HMRF) Grant from the Department of Communities & Local Government (CLG) for Liverpool and the Newheartlands pathfinder for the period 2008/11(NH/29)Report 7 pages DownloadRead as text

At this meeting

Whole meeting
214Minutes of the Last MeetingApproved 215aLocal Area Agreement 2008-2011 - Agreement of Priority IndicatorsApproved 215bDisposal of Sefton Grange (RES/61)Decided 215cLand Fronting Church Road (RES/62)Agreed 215dFirehouse Public House (RES/63)Decided 215eSheila Kay Day Centre and Toxteth Market (RES/64)Agreed 215f100 Cranmer Street (RES/65)Decided 215gCommunity Support Services Tender Process (HASC/14)Approved 215hStonebridge Cross Regeneration Project (NH/28)Agreed 215iBig Lottery Fund PE and Sport: Capital Programme Final Update (CHS/42)Noted 215jLiverpool Attendance Strategy (CHS/45)Approved 215kBuilding Schools for the Future (Wave 2): Enabling Works Contracts (CHS/46)Decided 215lSLEGI Commissioning Report 5 (EDE/25)Decided 215mCommissioning of Deprived Area Fund & Working Neighbourhoods Fund Projects (EDE/26)Decided 215nParks & Environment Service Capital Programme 2008/09 (E/9)Decided 216Higher Education Funding Scrutiny Panel - Final Report - Regeneration and Economic Development Select Committee 25 February 2008Agreed 217City Centre Movement Scrutiny Panel - Final Report - Regeneration and Economic Development Select Committee - 25 February 2008Agreed 218Childhood Obesity Scrutiny Panel - Final Report - Children's Services Select Committee - 3 April 2008On the agenda 219Exclusion of Press and PublicDecided 220aCruise Liner Facility (REG/57)Private 220bMajor Street Performance Event (L&CS/23)Private
222aAccepting the Housing Market Renewal Fund (HMRF) Grant from the Department of Communities & Local Government (CLG) for Liverpool and the Newheartlands pathfinder for the period 2008/11(NH/29)This decision
222bRoyal Liverpool Philharmonic Society Enhancement Contract (L&CS/22)Decided 222cLocal Authority Business Growth Incentive Scheme (EDE/27)Decided

Who was there

13 of 17 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
FC
Councillor Flo Clucas OBEMember, present
CE
Councillor Colin EldridgeMember, present
MF
Councillor Marilyn FieldingMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
TH
Tony HunterOfficer, apologies
PH
Phil HalsallOfficer, present

All 17 on the meeting page

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies