Resolved that - (i) the proposals for additional public realm costs for Waterfront Environmental Improvements, Waterfront Connections 2 and Strand be approved; (ii) subject to the receipt of revised offer letters, revised grant offers be accepted as outlined in the financial implications submitted made up of a maximum additional £ 1,303,465 ERDF and £ 1,517,185 NWDA funding; (iii) the Capital Programme be amended to reflect these offers; (iv) the additional expenditure at Pier Head/Mann Island Public Realm Waterfront Connections 2 and Strand as detailed above be committed; (v) the Team Leader, City Centre Projects Team be the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises. A&D/60
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Purpose To update Members on fully resourced additional expenditure in the Waterfront and Strand areas and financial changes to various projects at the Pier Head including Pier Head Public Realm, Waterfront Connections 2 and the Strand CCMS.
Background
In July 2006 Members approved the design, procurement and delivery strategy for public realm works in association with the Liverpool Canal Link at Pier Head and the Mann Island mixed use development to the value of £6.5m funded by NWDA and ERDF. The works at Pier Head are being delivered by British Waterways as part of the Liverpool Canal Link Contract and at Mann Island by Countryside Neptune LLP. An update report was received by Members in November 2007 which reported increased costs to reflect changes to project scope, accepted additional grant and updated financial profiles.
Pier Head Public Realm The first phases of public realm opened to the public on 28th October and 19th December and were acclaimed by all as a great success with many compliments being received for the exceptionally high quality of design, detailing and construction. The site was used successfully for the Transition event on 10th January 2009. Since initial funding approvals this project has increased in cost on three accounts • An increase in scope to include the external works to the new ferry terminal being brought forward by Merseytravel • An extension to the programme mostly due to delays to the ferry terminal • An increase in supervision costs associated with the delivery mechanism and need to attain exceptionally high quality standards
Mann Island The Pier Head public realm project also includes for public realm works around the canal basin at Mann Island to be implemented by Countryside Neptune LLP. Recent increases are forecast to the cost of construction of the stepped area of public realm adjacent to the canal basin.
Officers have worked with funding bodies over the life of the project to ensure that any overspend was fully funded. Agreement is now reached and revised offer letters/deeds of variation have been received from The Government Office and are awaited from NWDA.
Additional funding of £1,517,185 is available from NWDA is to be delivered by a range of measures across several approvals – Waterfront Environmental Improvements, Strand and Waterfront Connections 2.
Additional spend on existing programmes in the area, along with the agreement to include Grosvenor expenditure on James Street Interchange as match has enabled further ERDF funding to be secured in 2008/09. Total ERDF contributions to these projects have increased by £1,303,465 from £3,250,000 to £4,553,465. This contribution has been achieved on the basis of actual committed expenditure on site to the end of December 2008 and it has been agreed with other agencies to use this added money to further enhance the public realm works at Mann Island, the Strand and the Pier Head. This by product of negotiations with agencies will therefore be committed to additional paving, resurfacing and lighting works during the last quarter of 2008/09 and in 2009/10.
Adjustments to funding packages will be achieved as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.