Resolved that in connection with the Housing Market Renewal Initiative (HMRI) Programme 2009/10 authority be granted to commit and spend up to £20million in 2009/10. This involves a risk to the authority until the HMRI grant is confirmed but will ensure that the momentum of the HMRI programme is maintained. The risk of the grant not being confirmed is considered to be minimal.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The HMRI programme is 100% grant funded and has ongoing commitments which span financial years. This leaves little scope for other options to be considered as spending on items such as salaries and security of void property must continue.
Consultation
Regeneration Finance, NewHeartlands and the Accountable Body Monitoring Team have all been consulted over the preparation of this report and agree to these recommendations being made.
Consultation with Ward Councillors and outcome: Ward Councillors are regularly consulted and engaged on the proposals for their wards, through a variety of ways including member briefings, Design Working Groups, neighbourhood planning and other community consultation and engagement events. Financial implications:
On 25th April 2008 the Executive Board resolved that subject to the Executive Director (Regeneration) and the Acting City Solicitor agreeing the Deed of Variation to the existing ODPM (now CLG) funding Agreement, and on the receipt of offer letters from CLG, authority be granted to accept additional CLG grant of £ 152 million and be phased over the financial years 2008/09 (£54m), 2009/10 (£51m) and 2010/11 (£47m) towards the cost of the HMRI Implementation Programme. The 2008/09 allocation is a firm commitment but the 2009/10 and 2010/11 allocations are indicative and are subject to a +/- 10% variance.
On the 4th June 2008 the NewHeartlands Board approved the allocations for the HMRI 2008/09 programme and also approved the indicative allocations for 2009/10 and 2010/11. On 12th September 2008 the Executive Board approved the Liverpool HMRI Delivery Plan 2008-11 and amended the council’s capital and revenue budgets to include a total of £31.24 million in HMRI grant funding. Report SSC/12 also stated that further reports would be submitted in relation to 2009/10 and 2010/11 funding following confirmation of the resources available.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.