Resolved that in connection with the Churchill Flyover – Phase 3 City Centre Feature Lighting - (i) the City Council’s Highways Lighting Maintenance budget accommodates the running costs of £2,050 per annum for a period of 10 years. Following this 10 year commitment, a review will be undertaken to reassess the scheme and subsequent financial obligations; and (ii) it be noted that an order will be placed with Enterprise Liverpool under the Strategic Services Contract for the works. SSC/32
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
On 24th October 2008 a paper was submitted to Executive Board to inform Members of the ‘Pool of Light’ Festival, and to seek approval for Liverpool City Council to act as the Accountable Body for Phase 3 City Centre Feature Lighting (CCFL) Programme. The scope of the Phase 3 CCFL Programme includes 3 structures; Victoria Building, Engineering Building and Churchill Way Flyover. Approval to proceed was granted for both the Victoria Building and the Engineering Building. The Churchill Way Flyover scheme was deferred for clarification of revenue implications for the City.
This paper addresses the Churchill Way Flyover scheme only as there is no revenue implication for the City to consider for the Victoria Building or the Engineering Building as these structures are owned and serviced by The University of Liverpool.
The improvements to the Churchill Way Flyover consist solely of the introduction of a feature lighting scheme on the South Flyover structure. This scheme will be wholly funded from an overall allocation of the £500,000 earmarked for the CCFL Programme by the North West Development Agency (NWDA).
The NWDA funding must be expended before the end of the current 08/09 financial year. The NWDA funding is subject to a caveat that Liverpool City Council will cover the operational and maintenance costs associated with this scheme for a period of 10 years from within its revenue budget.
2.0Purpose
The purpose of this paper is to: § Respond to the request made at the previous Executive Board Meeting [Agenda Item E (iv)] on the 24th October 2008; this paper provides information on the revenue implications for the proposed scheme. § To gain Executive Board approval to include the proposed scheme into the current and future revenue budgets. § To enable Enterprise Liverpool to procure materials, carry out the works on the Churchill Way Flyover scheme and funding to be spent before the end of March 2009.
3.0Funding
Liverpool City Council and Liverpool Vision have been successful in obtaining £500,000 from NWDA to deliver the Phase 3 CCFL works, £210,000 of this funding is required to deliver the Churchill Way Flyover project.
However, there are tight spending conditions on this NWDA Funding: § All money must be spent before the end of the current financial year § Liverpool City Council’s Highways Lighting Maintenance revenue budget accommodates the maintenance and operational costs of the lighting scheme for a 10 year period.
4.0Delivery Programme
In order to achieve the spend target, the Principal Contractor must be appointed as soon as possible to enable procurement of the lighting elements (6-8 week manufacture and delivery) and complete the installation in the current financial year.
5.0Design and Procurement
The proposed lighting scheme will include the introduction of the following elements for the South Flyover Structure: § Down-lighting the 4 central columns § Up-lighting the underside of the central flyover structures § Lighting the south parapet handrails
As the flyover is located next to a conservation area and in close proximity to a major junction and pedestrian crossings, the use and type of lighting was carefully considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.