Liverpool City Council
Cabinet 2010/21, Friday 23 March 2018

Primary Expansion Programme - Blackmoor Park Infant School (M/31)

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 23 March 2018. Below is the council's own wording, with the papers it was decided on.

Item95g

Resolved

To seek authority to enter into a contract with Kier Construction (Liverpool) under the Scape Minor Works Framework, to construct a 3 classroom extension together with learning resource areas and ancillary spaces at Blackmoor Park Infant School to replace an existing suite of mobile classrooms
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 5 pages

CABINET

YEW TREE WARD PUBLIC M/31

Cabinet Member: Joe Anderson OBE, Mayor of Liverpool

Director: Nick Kavanagh, Director – Regeneration & Employment Services

Purpose of Report: To seek authority to enter into a contract with Kier Construction (Liverpool) under the Scape Minor Works Framework, to construct a 3 classroom extension together with learning resource areas and ancillary spaces at Blackmoor Park Infant School to replace an existing suite of mobile classrooms

Date: Report No: 23rd March 2018 EDR/15/18

Decision Type: Cabinet Key Decision

Executive Summary: Year 2 in Blackmoor Park Infant school is currently accommodated in a mobile classroom block. These have been identified as a priority for replacement based upon condition need and the works form part of the Council’s 5 year Schools’ Capital Programme.

Authority is sought to enter into a works contract with Kier Construction which will involve the demolition of the existing mobiles and their replacement with a permanent build comprising 3 classrooms, learning resource and wc’s.

Information: The proposed works comprise the construction of a new 3 classroom block extension with ancillary wc and learning resource space to replace an existing mobile classroom block that has reached the end of its useful life. This block is of ply construction and in recent years has been in need of regular repair to replace rotten timbers and deal with roof leaks. The permanent build is of modular construction and will be located in the same place as the existing mobiles and connected to the school. Temporary accommodation will be brought onto the site to decant year 2 whilst the works are in progress.

Planning approval for the project was granted on 1st February 2018

Recommendation: That –

(i) in respect of works to Blackmoor Park Infant School, authority be granted for the City Council sign a Memorandum of Agreement (construction contract) with Kier Construction (Liverpool) under the Scape Minor Works Framework up to a maximum contract value of £1,615,000 (including expenditure committed and spent through pre- construction stage Project Orders). In lieu of a bond, a Parent Company Guarantee is to be provided by the contractor;

(ii) authority be granted to commit expenditure up to a value of £1,650,000 to be financed from the City Council’s approved 2018/19 School Condition Allocation. The expenditure comprises the total design and construction costs of £1,615,000 to Kier plus contract administration and statutory fees; and

(iii) the Council’s Capital Programme be amended accordingly and authority granted to commit the expenditure as detailed within the report submitted.

Financial Implications: CAPITAL

The capital costs for the programme and forecast expenditure is set out below:

Forecast Contract Sum* £1,615,000 Technical Support £ 30,000 Ancillary Costs £ 5,000

Total £1,650,000

Financed by:

School Condition Allocation £1,650,000

*(including approved pre-construction expenditure of £131,258 and an enabling works contract of £486,631) Revenue There are no direct revenue implications for the Council in relation to these proposals.

Impact: The existing mobile classrooms have reached the end of their useful life. In addition to the resource pressures being placed on the school given the need for ongoing repair, the classroom environment is less than ideal. The new classrooms have a design life of 60 years and will provide space much more conducive to the delivery of the infant curriculum as well as enhancing the Council’s asset.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Primary Expansion Programme: Blackmoor Park Infant School (M/31)Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Primary Expansion Programme - Blackmoor Park Infant School (M/31)This decision
  2. Primary Expansion Programme - Monksdown Primary School (M/32)Approved
  3. Primary School Expansion Programme – Award of Construction Contract, Sudley Infant School (RTC/53)Approved
  4. Primary School Expansion Programme – Award of Construction Contract, Liverpool College (RTC/54)Decided
  5. Primary School Expansion Programme – Award of Construction Contracts, Smithdown Primary and St Silas CE Primary (RTC/35)Decided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies