Primary School Expansion Programme – Award of Construction Contracts, Smithdown Primary and St Silas CE Primary (RTC/35)

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 22 January 2016. Below is the council's own wording, with the papers it was decided on.

Item76b

Resolved

The report seeks authority to award the construction contracts for works at: · St Silas CE Primary School · Smithdown Primary School
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 10 pages

Executive summary

Following the completion of pre-construction activity, this report seeks authority to award the construction contracts for works at:

 St Silas CE Primary School  Smithdown Primary School

The projects being included within the first phase of the Primary School Expansion Programme

Background Information

On 19th December 2014 the Cabinet approved a recommendation that the City Council publishes statutory proposals to make prescribed alterations to enlarge the premises of Smithdown Community Primary School to enable the capacity of the school to increase from 210 to 420 phased over seven academic years commencing in September 2015;

On 1st February 2015 St Silas CE Primary converted to an academy in tandem with the approval by the Education Funding Agency of the expansion of the school from 1 to 1.5 forms of entry (210 to 315) pupils.

The expansion of both schools is included in phase 1 of the City Council Primary Expansion Programme.

Following the expiry of the statutory consultation period and in the absence of objections, the expansion of Smithdown Community Primary along with St Anne’s RC Primary and St Cleopas CE Primary were approved by the Director of Children’s and Young Peoples Services under powers delegated by Cabinet.

In addition, following the receipt of representations made during the consultation for Christ the King RC Primary and Dovedale Infant and Junior Schools the Cabinet also approved the prescribed alterations in respect of both schools on 20th March 2015.

Construction contracts in respect of the first four schools St Anne’s RC Primary, St Cleopas CE Primary, Christ the King RC Primary and Dovedale Primary have been awarded and this report seeks approval to the award of the final two construction contracts of the first phase of the Primary Expansion Programme in respect of Smithdown Primary and St Silas RC Primary schools.

Project Proposals

1. St Silas CE Primary

The project comprises the construction of a 2 classroom extension together with resource and ancillary space to replace an existing mobile unit, together with a single storey hall extension and associated external works. The project will commence in April 2016 to be completed by the end of August 2016.

Planning approval was granted on 5th November 2015

2. Smithdown Primary School

The project comprises the construction of a single storey foundation stage incorporating 2 reception classrooms and nursery; a parent link and student support extension; internal remodelling throughout to create the additional classrooms and ancillary spaces and associated external works. Works to replace and upgrade the school drainage system and resolve long standing heating problems will be undertaken at the same time.

The project is due to commence in the February 2016 half-term and be completed by the end of August 2016. Planning approval was granted on 9 November 2015.

Procurement

Pre-construction orders have been placed with Kier Construction under the Scape Minor Works Framework to develop the projects up to the point of contract award.

This report seeks authority to award the construction contracts for the main works through to completion.

Timescales

Contract award for the 2 projects identified above is planned for February 2016 for completion of all works by September 2016.

Costs

The total construction costs for the schemes (including pre-construction expenditure committed to date and contract administration fees) are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Primary School Expansion Programme: Award of Construction Contracts, Smithdown Primary and St Silas CE Primary (RTC/35)Report 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Primary School Expansion Programme – Award of Construction Contracts, Smithdown Primary and St Silas CE Primary (RTC/35)This decision
  2. Wavertree Primary School – Extension Refurbishment (E/14)Decided
  3. Permission to post Statutory Notices – Proposal to expand Blueberry Park Primary School (E/15)Decided
  4. Proposal to Expand Blueberry Park Primary SchoolAgreed
  5. Publication of Statutory Proposals - Changes to Language Resourced Provision at Four Oaks Primary School (E/15)Decided
  6. Community Primary & Secondary Schools Admission & Co-ordinated Admission arrangements 2020/21(E/7)Decided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies