25/503438/FULL Land At Eastwood Road, Ulcombe, Maidstone, Kent, ME17 1ED
RefusedPlanning3 papers
AI summaryMaidstone Planning Committee refused planning permission for a residential development at Eastwood Road, Ulcombe, citing harm to the countryside character of the village. The vote was unanimous, 10 in favour of refusal.
MoneyNo primary, 3 secondary pupilsKCC requested secondary education places only
What happens nextNot stated
Who it affectsEastwood Road, UlcombeLand south of the village settlement
What was decided
The committee refused planning permission. The vote was 10 in favour of refusal, 0 against and 0 abstentions.
The reason for refusal is that the development's scale, layout, location, domestic paraphernalia and lighting would urbanise the site and look out of place with the pattern and grain of development in the immediate surroundings.
The committee found the development would be a significant protrusion of the settlement southwards, beyond most of the existing development in Ulcombe, causing significant harm to the character and appearance of the countryside.
Why
The development would fail to conserve the rural setting of Ulcombe village and its built form, according to the decision.
Officers considered the scheme contrary to policies LPRSS1, LPRSP8, LPRSP9, LPRSP15 and LPRQD4 of the Maidstone Borough Local Plan Review (2021 to 2038), the Council's Landscape Character Assessment (2012), and the National Planning Policy Framework (2024).
The committee concluded that granting permission and providing housing would not significantly and demonstrably outweigh the harm identified.
The money
£4,686,017 (strategic element) as of 31/03/2025 CIL strategic funding pot balance cited by KCC, described by officers as out of date Report P12
£7,208,296.13 Current CIL funding held by Maidstone Borough Council from development Report P12
£1,535,034.89 Further CIL funding provided directly to communities, for example parish councils Report P12
£8,743,331.02 Total current CIL fund for infrastructure held or allocated by the council Report P12
£96,551,627 as of December 2022 Infrastructure funding gap identified in the Infrastructure Delivery Plan Report P12
Implications
Legal: The refusal cites five Local Plan Review policies, the Council's Landscape Character Assessment (2012) and the National Planning Policy Framework (2024) as the planning basis.
Financial: Kent County Council sought education contributions via a Section 106 agreement or equivalent CIL funding; the officer view is that the lack of a Section 106 contribution for education is not contrary to policy and is not grounds to refuse the application. Report P7, P8, P9, P10, P13
Other: The site is identified as a significant southward extension of the Ulcombe settlement, which the committee found harmful to the rural setting.
Who and where
The applicant for 25/503438/FULL
Residents of Ulcombe and the surrounding countryside
Kent County Council, as the education authority for the area Report P4, P5, P6
Timeline
December 2022: Infrastructure Delivery Plan funding gap figure cited by KCC Report P12
31/03/2025: CIL strategic funding pot closing balance reported by KCC Report P12
26th March 2026: Planning Committee meeting and decision to refuse Report P1
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge on development used to fund infrastructure
s106: Section 106 Agreement, a legal planning obligation used to secure site specific contributions
SEND: Special Educational Needs and Disabilities
NPPF: National Planning Policy Framework
KCC: Kent County Council
MBC: Maidstone Borough Council
IDP: Infrastructure Delivery Plan
Local Plan Review: Maidstone Borough Local Plan Review covering 2021 to 2038
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item251
Resolved
That permission be refused for the following reasons: That the proposed development, by virtue of its scale, layout, and location, together with its domestic paraphernalia and lighting, would result in urbanising development that would appear incongruous with the pattern and grain of development within the site's immediate surroundings. This significant protrusion of the settlement southwards, beyond most of the existing development in Ulcombe, would cause significant harm to the character and appearance of the countryside hereabouts. This failure to conserve the rural setting of built form of Ulcombe village would be contrary to Policies LPRSS1; LPRSP8; LPRSP9; LPRSP15; and LPRQD4 of the Maidstone Borough Local Plan Review (2021-2038); the guidelines within the Council's Landscape Character Assessment (2012), where it seeks new development to conserve the rural setting and the predominant linear pattern of built form of Ulcombe village and the countryside; and the aims of the National Planning Policy Framework (2024), where it seeks to protect and enhance the natural and built environment. Granting planning permission and the provision of housing would not significantly and demonstrably outweigh the harm identified. Voting: 10 – For 0 – Against 0 – Abstentions
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
19/504724/HYBRID Land off Old Ashford Road, Lenham, Maidstone, Kent 25/502491/FULL Land At Postley Road, Maidstone, Kent, ME15 6RH 25/503438/FULL Land Adjacent to Eyhorne Street, Hollingbourne, Kent, ME17 1XA 25/504639/FULL Land At Eastwood Road, Ulcombe, Maidstone, Kent, ME17 1ED
Representations from Kent County Council (Strategic Development and Place)
Kent County Council (KCC) have made representations relating to all four of the above applications being considered on the Agenda.
All are residential developments where KCC have made requests for monies towards primary, secondary, and SEND education projects.
KCC are raising an objection to the grant of permission until such time as either:
a) Confirmation that the applicant and Borough are content to allow education to be secured through an accompanying s106; or
b) MBC provides the equivalent ringfenced levels of CIL funding for Education.
Officer Comment The Community Infrastructure Levy (CIL) adopted by the Council in 2018 is an appropriate mechanism to fund strategic infrastructure, such as education. Whereas financial contributions secured via a s106 Agreement are used to provide site- specific mitigation which will normally be provided on site but may where appropriate be provided in an off-site location or via an in-lieu financial contribution. It is possible to use both CIL and s106 contributions towards the same piece of site specific infrastructure provided there is no double-counting. This approach is in accordance with Local Plan LPRSP13 (Infrastructure Delivery) and LPRINF2 (Community Facilities) of the Local Plan Review. In respect of all four of the applications, the monies requested by KCC are towards off-site strategic education infrastructure projects (potential school expansions or unspecified in the case of SEND). These developments will add incrementally to the need for strategic infrastructure. For example, the expected pupil yield as set out by KCC for the applications are below and none are of a scale to require a school expansion in their own right. The identified Primary school project(s) are also the same for two of the applications and Secondary school projects the same for all applications.
Old Ashford Road: 28 Primary pupils and 20 Secondary pupils. Postley Road: 8 Primary and 6 Secondary. Eyhorne Street: 5 Primary and 3 Secondary. Eastwood Road: No money requested for Primary and 3 Secondary.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
24/500007/full - demolition of 5no.RESOLVED : 1. That subject to: A. The prior completion of a legal agreement in such terms as the Head of Legal Partne...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.