Medway Council
Cabinet, Tuesday 9 March 2010 at 3.00pm

Gateway 3 Contract Award and Gateway 4 Contract Review: Walderslade Primary School Rebuild

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 9 March 2010. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

50/2010 The Cabinet agreed to authorise the Director of Children and Adult Services, in consultation with the Portfolio Holder for Children’s Services, to appoint Mansells as the second stage contractor for the main works.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Background

2.1In August 2009 Cabinet approved the appointment of a preferred contractor for pre-construction works. This resulted in the appointment of Mansells Construction Services to provide input to progress some of the complex design and buildability issues relating to the complex site conditions.

2.2Following the completion of the pre-construction phase, a cost for works has been submitted by Mansells and approved by an independent firm of quantity surveyors. By involving the preferred bidder in the pre-construction phase, including the detailed development of the design and assessment of site issues, this enables the contractor to provide a fixed price for the overall cost of construction.

3. Related Decisions

3.1In August 2009 Cabinet was provided with details of the proposals for the commissioning of pre-construction and the main works for the rebuild of Walderslade Primary School. At this meeting Cabinet made a number of recommendations, which have been progressed as follows:

a) Authorise the Director of Children and Adult Services in consultation with the Portfolio Holder for Children’s Services to appoint the recommended preferred bidder for pre-construction works, using the contract form specified by the IESE framework;

This has been undertaken using the IESE Pre-Construction Agreement. Mansells Construction Services Ltd were appointed the preferred bidder to undertake Pre-Construction works providing services that included the following: - Advising the team on the practical implications of the design proposals - Assessing Buildability issues - Developing a cost plan by adding in preliminary costs and benchmark data. - Advising on supply chain strategy - Producing of individual package tender reports

b) Delegate authority to the Director of Children and Adult Services in consultation with the Portfolio Holder for Children’s Services to make any appropriate linked contractual arrangements with preferred bidder and third parties;

In developing the proposals a number of other contractual arrangements were identified as being required. These were - Appointment of EDF to carry out the relocation of power cables to allow the new build to be undertaken. - Commitment to Highways to appoint a consultant to review the design adjacent to the highway

c) In the event that the preferred bidder is unable to deliver, delegate authority to the Director of Children and Adult Services in consultation with the Portfolio Holder for Children’s Services to appoint the reserve in their place

The successful appointment of Mansells Construction Services Limited as the preferred bidder and their delivery to date has meant that there has been no requirement to appoint a reserve.

d) Delegate authority to the Director of Children and Adult Services in consultation with the Portfolio Holder for Children’s Services to commission where there is a clear economic advantage, early works packages to a maximum aggregate value of £500,000;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award and Gateway 4 Contract Review: Walderslade Primary School RebuildReport 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, present
RC
Councillor Rehman Chishti (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Philip Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
RC
Rose CollinsonOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contract Award and Gateway 4 Contract Review: Walderslade Primary School RebuildThis decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies