Cabinet, Tuesday 25 August 2026 at 7.00pm

Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build Project

Agreed Executive 1 paper

AI summaryMedway Cabinet has awarded the pre-construction and design contract for the new Danecourt Secondary SEND school to Morgan Sindall, in a £1.8m direct award via the Pagabo framework, with potential project savings of up to £1.37m and delivery at least two years sooner.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedMost economically advantageous under Pagabo direct award
Money£1.8m for this stageFunded from existing grants, no new borrowing
What happens nextConstruction contract stage to followTwo stage procurement, second stage in due course
Who it affectsAround 250 SEND secondary placesPlus families using out of area independent provision

What was decided

Cabinet agreed to award the Pre-Construction and Design Development contract to Morgan Sindall, following evaluation as the most economically advantageous bidder under the Pagabo Major Projects framework. Report 1.1, P15

The decision accepts potential whole-project savings of £825,000 to £1,368,000 identified through supply chain efficiencies, shared access with the adjacent Inspire School, and reduced lead times. Report 7.2, P48

Contract management will sit with the Strategic Head of Education, Planning and Access and the Education and SEND Capital Programme Lead. Report 4.3, P22

Why

The chosen provider scored highest against the evaluation criteria and the consultants' control option in the exempt spreadsheet. Report 1.1

Officers cited supply chain efficiencies, economies of scale, site risk management, design and pre-construction fees, and shared amenities with the adjacent Inspire School as the basis for significant savings. Report 2.1, P48

Running Danecourt concurrently with the DfE appointed Inspire School build on the same site is expected to cut delivery by at least two years, helping meet a statutory duty to provide places by September 2029. Report 7.3, P50, P24

What happens next

Proceed with the pre-construction and design development work; the construction contract award will follow as a separate Gateway decision. Report 3.2, P10

Procurement Board and Monitoring Officer will set risk and reporting stages for the Gateway 4 process. Report P38

Further funding may be sought via the Annual Review of the School Place Planning Strategy 2026, with the current approved budget at £25m. Report P32

The money

  • £1.8m Cost of the PCSA procurement stage, funded from existing grants Report P31
  • £825,000 to £1,368,000 Potential savings identified for the whole project Report 7.2
  • £16.21m Borrowing approved by Cabinet on 26 August 2025 for the project Report P2, P29
  • £911k per annum Estimated annual cost of borrowing £16.21m over 50 years Report P30
  • £45,57m Total estimated borrowing cost over 50 years at £16.21m Report P30
  • £25m Current approved budget for the project Report P32
  • £21.8m Current annual cost of 420 pupils placed in independent schools in and outside Medway Report P51
  • £12m per annum Future cost avoidance once Danecourt expansion is at full capacity Report P52
  • £11m per annum Net annual saving after borrowing costs Report P52
  • £796,250 per annum Estimated home-to-school transport savings at full capacity
  • £1.4 million Estimated cumulative transport saving over the six year phased admissions period from earlier delivery Report P55

Options considered

  • Rejected: SCAPE framework. Only allows NEC contracts which are not appropriate for this project, and is the most expensive option Report P17
  • Rejected: NHS SBS framework. Provider did not respond to enquiries Report P18
  • Rejected: Southern Construction Framework. Lower 0.25% fee but charged partly at PCSA stage; not preferred over Pagabo Report P19
  • Chosen: Pagabo Major Projects framework, direct award to Morgan Sindall. 0.3% framework fee charged only at main contract stage, so no fee if project stops after PCSA; enables co-ordination with the adjacent Inspire School Report P20, 6.6, 7.3, P50

Implications

  • Financial: The £1.8m PCSA cost is funded from existing grants rather than borrowing, so this stage adds no new interest costs. Report P31
  • Financial: Borrowing of £16.21m over 50 years is estimated to cost £911k per year, or about £45,57m in total. Report P30
  • Legal: Procurement was above the FTS threshold and complied with the Public Contracts Regulations 2015 and Medway's Contract Procedure Rules, including a Process 3 procurement under Rule 18. Report P33, P35, P37, P38
  • Legal: Medway has the power to enter the contract under the Local Government (Contracts) Act 1997 and the Localism Act 2011. Report P36
  • Risk: Budget overrun risk rated B2, mitigated by detailed surveys, costed feasibilities, regular monitoring and ongoing value engineering across the whole project. Report P25
  • Risk: Reputational risk rated B2 if the Council fails to provide sufficient school places; the project supports the statutory duty to provide places by September 2029. Report P24
  • Equalities: The expansion will create around 250 additional SEND secondary places, helping to reduce reliance on out-of-area and independent placements for children with EHCPs. Report P9, P51
  • Staffing: Contract management will be the responsibility of the Strategic Head of Education, Planning and Access and the Education and SEND Capital Programme Lead. Report 4.3, P22

Who and where

  • Medway secondary age children with EHCPs, including the 343 additional pupils expected over the next five years Report P51
  • Current 420 pupils placed by Medway in independent schools in and outside the area, and their families Report P51
  • Medway Council Education and SEND service, which will manage the contract Report 4.3, P22
  • Construction supply chain and design consultants engaged on the PCSA and future main contract Report 2.1, P48

Timeline

  • 26 August 2025: Cabinet approved borrowing of £16.21m for the Danecourt Special School project under decision 117/2025 Report P2, P29
  • 23 September 2025: Cabinet considered Gateway 1 BN and SEND Capital Programme 2025-30 Report P59
  • 25 August 2026: Cabinet decision 130/2026 to award the PCSA contract to Morgan Sindall
  • By September 2029: Statutory deadline for providing sufficient school places, driving the timeline Report P24
  • Six year phased opening: Danecourt will admit one year group at a time once open, taking six years to reach full 250 place capacity Report 7.4, P54

Plain English for the jargon

  • PCSA: Pre-Construction Services Agreement, covering design development before the main build contract
  • SEND: Special Educational Needs and Disabilities
  • EHCP: Education, Health and Care Plan, the formal plan for a child or young person with SEND
  • FTS: Find a Tender Service, the UK portal for higher value public sector procurements
  • Pagabo: A construction framework used for major projects, used here for a direct award
  • PCG: Parent Company Guarantee, a financial guarantee from the contractor's parent company
  • S106: Section 106 planning obligation payments from developers, used here as a funding source
  • BN: Basic Need, central government grant for additional school places
  • CPRs: Medway Council's Contract Procedure Rules
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

130/2026 The Cabinet agreed to award the contract to Morgan Sindall as they had been evaluated as the most economically advantageous against the consultants control option and award criteria as per the evaluation spreadsheet contained within 3.1 of the Exempt Appendix. Reasons: The construction company has identified significant savings that can be achieved in financial and lead times. This is evidenced in their proposals and is achieved via the following: Supply chain efficiencies, economies of scale, site risks and constraints, design and pre-construction fees, speed of delivery and preliminary costs, as well as shared access and amenities/services with another new build school being built on the adjacent site by the same provider.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission to award the procurement of the Pre-Construction and Design Development (PCSA) for the Danecourt Secondary New Build Contract.

The Basic Need and SEND grant funding are ringfenced to Education for the purpose of providing additional school places, in addition, a commitment to borrow £16.21m for the Danecourt Special School project was approved by Cabinet on 26 August 2025 under decision 117/2025.

Recommendation

1.1It is recommended that the Cabinet agrees to award the contract to the supplier named in 3.2 of the Exempt Appendix as they have been evaluated as the most economically advantageous against the consultants control option and award criteria as per the evaluation spreadsheet contained within 3.1 of the Exempt Appendix.

2. Suggested reasons for decision

2.1The construction company has identified significant savings that can be achieved in financial and lead times. This is evidenced in their proposals and is achieved via the following: Supply chain efficiencies, economies of scale, site risks and constraints, design and pre-construction fees, speed of delivery and preliminary costs, as well as shared access and amenities/services with another new build school being built on the adjacent site by the same provider.

3. Background Information 3.1. Budget & Policy Framework

3.1.1. Proposals that flow from the School Place Planning Strategy 2022-27, its forerunners the School Place Planning Strategy 2017-22, the School Organisation Plan 2011-16 and its subsequent annual reviews are consistent with the School Organisation Plan Principles and with the Council Plan Priority outcome of ‘All children achieving their potential in schools’. The proposals will only be delivered within available funding.

3.2Background Information and Procurement Deliverables

3.2.1. The addition of a Danecourt secondary school is a high priority project for Medway. It will create an additional 250 SEND places which will significantly reduce the need to place children in expensive independent and out of area provisions in future years.

3.2.2. The project is based on a two-stage procurement process. This initial stage will determine the pre-construction sections of the process including design development. The second stage will be for the construction contract which will follow in due course.

3.3Parent Company Guarantee/Performance Bond Required

3.3.1. As per Gateway 1, PCG will be sought. In the event a PCG does not exist the service will defer to the JCT Retention Clause, as with the other activities.

4. Procurement Process

4.1Procurement Process Undertaken

4.1.1. Direct award via Pagabo Framework. 4.2. Evaluation Criteria Used

4.2.1. Framework options open to us for appointing a specific contractor under a direct award.

SCAPE - Framework fee is 0.5% of the contract, charged at 0.25% PCSA stage and 0.35% main contract stage. Only option is to use NEC contracts, which is not appropriate for this project. For this reason, we have not further considered SCAPE (it is also most expensive).

NHS SBS - This framework didn't respond to enquiries and therefore were not considered further.

Southern Construction Framework (SCF) - Framework fee is 0.25% which is charged at 25% PCSA stage and 75% main contract stage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectReport 271 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 15 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, apologies
HM
Councillor Harinder Mahil (Lab)Committee Member, apologies
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present
RH
Richard HicksOfficer, in attendance
RD
Ruth Du-LieuOfficer, in attendance

All 15 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectThis decision
  2. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  3. Gateway 1 Report: Highways Infrastructure ContractAgreed
  4. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  5. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed
  6. Gateway 3 Contract Award: Provision of Residential and Nursing Care for Older People (Aged 65+)Agreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies