Gateway 3 Contract Award: Recycling Resource Management (RRM) Procurement

Agreed Executive 1 paper

AI summaryMedway Cabinet awards the Recycling Resource Management contract to Veolia Environmental Services, the only compliant bidder, with the new deal starting on 1 October 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedOnly compliant tender received in open single stage process
MoneyNot stated in public papersFinancial details in Exempt Appendix; funded from existing Waste Disposal budget
What happens nextNew contract starts 1 October 2026Initial term to 30 September 2029, with possible 36 month extension
Who it affectsMedway household waste and recycling serviceAround 156,000 tonnes of material expected over the contract life

What was decided

The Cabinet agreed to award the RRM contract to Veolia Environmental Services, the only fully compliant bidder, with the award based on the published evaluation methodology. Report P50

Members accepted that a re-tender was not recommended, as it was unlikely to attract further bids and would risk service disruption and extra cost. Report P32

The award was made to maintain Medway's statutory recycling and waste treatment obligations from 1 October 2026. Report 4.5

Why

Veolia was the only organisation to submit a tender that met all mandatory and technical requirements set out in the specification. Report P50

The procurement exercise showed limited market interest, reflecting the specialist nature of the service and current market capacity. Report P32

Veolia operates around 22 contracts across London and the South, including two in Kent (Medway and Dover & Shepway), giving relevant regional experience.

What happens next

The new contract is due to commence on 1 October 2026 and run to 30 September 2029, managed by the Waste Disposal Manager. Report P8, 8.1, P21

A decision on whether to use the available extension must be made by March 2028; if not extended, reprocurement must start in April 2028. Report P20, P21

Quarterly monitoring of the contract will be carried out by the Waste Disposal Team and FLS program board, with a Gateway 4 review at the end of the contract. Report P8, P22

Options considered

  • Chosen: Award contract to Veolia Environmental Services. Only compliant tender; meets all mandatory and technical requirements and supports statutory obligations Report P50
  • Rejected: Re-tender the service. Unlikely to attract further bids given market constraints and would risk service disruption, extra cost, and missed statutory deadlines Report P32

Implications

  • Financial: The contract will be funded from within the existing Waste Disposal budget; any future pressures will need to be addressed in the 2027/28 budget build. Report P41
  • Legal: The process complied with the Procurement Act 2023, the Council's Contract Procedure Rules, and FTS requirements; legal and procurement specialists reviewed key documents. Report P27, P42, P44, P45, P46
  • Climate: The contract supports the Council's Climate Change Action Plan (2025-28), the Resource Efficiency priority, and a low carbon waste management system, with carbon reporting built in. Report 10.5, P29, P30, P52
  • Risk: Single supplier dependency is a recognised market capacity risk (rated C III) and will be mitigated through ongoing performance monitoring and benchmarking. Report P32
  • Risk: Mobilisation, service delivery, and indexation risks are rated C II to C III, with mitigation through mobilisation plans, KPIs, and use of market indices. Report P28, P31, P35, P36
  • Other: There are no TUPE implications arising from this procurement. Report 10.3, P49

Who and where

  • Medway residents using the kerbside recycling service (white/clear bag, blue bag, and brown bag/bin/caddy collections) Report P3
  • Medway Council Waste Disposal team, which will manage the contract Report 8.1, P54
  • Veolia Environmental Services, which will deliver the contract

Timeline

  • 31/10/2025: FTS notice issued and ITT started Report P14
  • 31/10/2025, 14/11/2025: Clarification period Report P14
  • 05/12/2025: Tender submission deadline Report P14
  • 05/12/2025, 05/01/2026: Evaluation period Report P14
  • 06/01/2026: Moderation period Report P14
  • 05/05/2026: Cabinet decision to award the contract
  • 01/10/2026: New RRM contract commences Report 4.5, P8, P21
  • March 2028: Decision date on whether to use the contract extension Report P20, P21
  • 30/09/2029: Initial contract end date (with up to 36 month extension available) Report P21

Plain English for the jargon

  • RRM: Recycling Resource Management, the council's contract for transferring and treating household recyclables
  • FTS: Find a Tender Service, the UK public sector procurement notice portal
  • ITT: Invitation to Tender
  • KPI: Key Performance Indicator used to monitor contract delivery
  • LGR: Local Government Reorganisation, referenced as a factor in procurement planning
  • PCG: Parent Company Guarantee, which was waived for this procurement
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations, which do not apply here
  • CPRs: Medway Council's Contract Procedure Rules
  • Gateway 4 (GW4): Final review stage in the council's procurement process before contract end
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

79/2026 The Cabinet agreed to award the contract to the bidder Veolia Environmental Services, whose submission was the only compliant tender received and, in line with the published evaluation methodology, had been assessed as meeting all required criteria for contract award, as set out in the Exempt Appendix. Reasons: The recommended supplier was the only organisation to submit a fully compliant tender that met all mandatory and technical requirements set out in the specification. The procurement exercise evidenced limited market interest, which is consistent with current market capacity and the specialist nature of the service. As a result, no alternative tenders were available for evaluation. The bid presents a robust, viable, and fully deliverable solution that will enable Medway to continue meeting its statutory obligations. It provides clear evidence of the supplier’s capability and capacity to deliver all aspects of the contract. The supplier currently operates around 22 contracts across London and the South, including two within Kent -Medway and Dover & Shepway -demonstrating strong regional experience and a proven track record in service delivery. A re ? tendering exercise would be unlikely to produce a different outcome given the market constraints already observed, and would introduce a significant risk of service disruption, additional cost, and potential failure to meet statutory or contractual deadlines. Awarding the contract at this stage is therefore the most appropriate, proportionate, and defensible route to secure the required services, maintain continuity of a critical statutory function, and ensure compliance with procurement regulations and internal governance requirements.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementReport 297 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, present
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, apologies
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present

On this subject at Medway

Search all
  1. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementThis decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Provision of Residential and Nursing Care for Older People (Aged 65+)Agreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies