54/2010 The Cabinet approved the amendments to the Council's Risk register as detailed in Section 3 of the report and set out in Appendix B to the report and agreed to delegate authority to the Director of Regeneration, Community and Culture to incorporate, within the risk register, the risk of a potential legal challenge to the waste contract and additional narrative where a risk’s rating had been increased . Reasons: The establishment of a corporate framework for risk management is recommended by CIPFA and SOLACE and will complement and support the work already being carried out within each directorate to manage risks.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
In accordance with paragraph 4.1 of the Council’s Risk Management Strategy, this report is to discuss the 6 monthly review of the Council’s Corporate Business Risk Register.
1. Budget and Policy Framework
1.1The Risk Management Strategy underpins all aspects of Council work and is fundamental to the Council Plan in terms of "giving value for money”.
Background
2.1The Corporate Risk Register was last reviewed by Cabinet on 3 November 2009. The following changes were made to the register at that time: • Risk Ref 03b – ‘Finance, Longer Term’ be updated to reflect the possible impact of future financial settlements. • Risk Ref 05 – ‘Waste Procurement’ be changed to reflect the current delay in awarding the contract. • Risk Ref 9a – ‘Delivering the Transformation Agenda’ be amended to reflect a refocusing of the work. • Risk Ref 16 – ‘Improvement Plan for Housing Services’ – the current risk rating of C2 be downgraded to D2 (Low likelihood/Critical Impact) to reflect the significant service improvement as recognised by two independent reviews. • Risk Ref 17 – ‘Delivering Regeneration’ be increased to B2 (High Likelihood/Critical Impact) to reflect potential delays to the delivery programme. • A new risk relating to procurement processes (risk reference 21) was added to the register. 2.2 The monitoring and escalation procedure, previously agreed by Cabinet on 31 March 2009 was amended to reflect the Council’s new performance management processes and systems.
3. Advice and analysis
3.1Risk owners have reviewed their risks and the Corporate Management Team (CMT) propose the following amendments which are summarised in Appendix A - Record of Amendments: a) Risk Ref: SR 03b – ‘Finances - longer term’: Increased from B2 to A1 to reflect increasing certainty that the financial outlook is poor with commentators agreeing that the next three years could see a 10/20% reduction in Local Government resources. b) Risk Ref: SR 04 – ‘Performance management’. Taking account of the mitigating actions in place, the risk rating be reduced from B2 to C2. c) Risk Ref: SR13 – ‘Equalities & Diversity’: The significance attached to effective monitoring of equality and diversity information about our customers and targeted action taken as a result is increasing as a result of the likely enactment of the Single Equality Bill in October 2010, greater focus on equalities in all inspection activity and improving performance across councils against the Equality Framework. Recent inspection and regulation activity in housing, adult social care and children's services has highlighted consistent equalities monitoring and use of the information as an area for improvement. Currently we are working towards 'achieving level' of the Equality Framework, which has already been achieved by a significant number of councils. In recognition of this 'raising of the bar' the risk rating has been increased to B2. d) Risk Ref: SR16 – ‘Improvement plan for housing services’: Remove as the outcome of the inspections shows that the risk no longer exists. e) Risk Ref: SR 20 – ‘Flu Pandemic’: Down grade from C1 to D2 to reflect significant reduction in concerns of the impact of the Swine flu virus. f) The addition of a new risk relating to treasury management - Ref SR 22 reflects the Council’s vulnerability should a bank that the Council has invested in fail or there are unexpected changes to interest rates. g) The recognition of the risk relating to the Improvement Plan for Housing Service (HRA).- Ref SR23. A peer review of HRA housing services identified a number of issues which could result in the Council receiving a poor inspection score should actions put in place fail to improve the service.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.