Cabinet, Tuesday 30 March 2010 at 3.00pm

Capital Budget Monitoring 2009/2010

Noted Executive 1 paper

Cabinet noted this item on Tuesday 30 March 2010. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

The Cabinet noted: a) The spending and funding forecasts summarised at Tables 1 and 2 of the report; b) Additions to the capital programme as detailed in section 5.1 of the report. 57/2010 The Cabinet authorised expenditure against the approved capital programme for 2010/2011 and future years. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Background

2.1This report consolidates the capital monitoring undertaken by each directorate, which is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.

2.2Medway Council has a capital programme for 2009/2010 now in excess of 200 individual schemes. Approximately 140 of these are principal schemes, i.e. over £100,000, including a significant number rolled forward from earlier years, and the substantial regeneration programme being progressed by the Medway Renaissance.

3. Progress

3.1Table 1 summarises the current overall expenditure and forecasts on capital schemes within each directorate for the 2009/2010 capital programme. This table summarises Appendix 1. Appendices 2 to 6 show the position by directorate. Table 1: Spend to Date

forecast to spend Commitments to Forecast spend

Variance (is an

in later years underspend) Programme

programme Spend and 2009/2010 Approved

Approved date Directorate

£’000 £’000 £’000 £’000 £’000 Business 19,398 12,573 7,482 165 6,990 Support Dept Children & 41,819 25,324 14,623 (177) 16,318 Adults Regeneration, Community & 91,033 35,440 22,127 (268) 55,325 Culture Members 2,958 1,493 854 0 1,455 Priorities TOTAL 155,208 74,830 45,086 (290) 80,088

4. Specific Scheme Monitoring Issues and Completions (By Directorate)

4.1The format of the electronic capital budget monitoring reports presented to the Directorate Management Teams includes a considerable amount of detail provided by the relevant capital project managers regarding individual scheme progress and achievement of milestones. As in previous reports the ‘at a glance’ progress monitoring system based on the following criteria provides some statistical data for this report.

☺ Scheme progressing on time and within budget

Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales

Scheme neither progressing within expected timescales nor within budget.

4.2Business Support Department

Total Progress Monitoring ☺ Schemes Business Support Department 27 2 0 29 4.2.1 There are no additions to the Business Support Capital Programme since the last report.

4.2.2 Good progress is being made on the New Medway Council website project, with the appointment of an external design agency partner.

4.2.3 The demolition of the former Civic Centre is progressing well.

4.2.4 The new library PCs have been installed, and are now awaiting peripheral hardware to complete the project.

4.3Children and Adults Directorate

Total Progress Monitoring ☺ Schemes Children and Adults 42 27 0 69

4.3.1 There have been no additions to the Children and Adults capital programme since the last report to Members.

4.3.2 Examples of good progress being made by capital projects within the Children and Adults Directorate since the last update include the following:

Two Childrens Centres, Riverside, and Deanwood, have been completed.

The building works at The Old Vicarage are nearing completion and it is planned that the service currently operating from The Ridgeway will return to Upnor on 26 March.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring 2009/2010Report 627 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, present
RC
Councillor Rehman Chishti (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
RC
Rose CollinsonOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Capital Budget Monitoring 2009/2010This decision
  2. Capital Budget Monitoring - Round 1 2026/27Noted
  3. Capital Budget Monitoring - Round 1 2026/27Noted
  4. Capital Budget Monitoring - Round 1 2026/27Noted
  5. Capital Budget Monitoring - Round 1 2026/27Noted
  6. Amendments to the Revenue Budget and Capital ProgrammeAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open