192/2010 The Cabinet approved the award of the additional works to Vital Technology and an exemption to contract rules to allow a variation of greater than 50% of contract value of the existing contract with Vital Technology. Reasons: To upgrade the tunnel systems as quickly and economically as possible and with the minimum disruption to traffic.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
To seek further improvements to the tunnel control system by means of a variation to the existing contract with Vital Technology.
1. BUDGET AND POLICY FRAMEWORK
1.1The funding for this work was provided by DFT and is part of the Capital Programme ring-fenced for Tunnel works. This proposal is therefore within that budgetary and policy framework.
1.2The Procurement Board has recommended that the variation by greater than 50% of contract value which requires an exemption approval be considered by the Cabinet.
2. RELATED DECISIONS
2.1A Gateway 3 report detailing the need for the replacement of the Medway Tunnel Electronic Control System was reviewed by Procurement Board on 14 October 2009 and passed by Cabinet on 3 November 2009. The contract was awarded to Vital Technology with a bid of £847,313.17. The awarded contract is of a ‘Design and Build’ type.
3. INTRODUCTION/BACKGROUND
Introduction
3.1The Head of Highways and Parking Services is now seeking further improvements to the tunnel control system and wishes to do this by means of a ‘Variation’ to the contract with Vital Technology. 3.2 The improvements that the Head of Highways and Parking Services seeks are:- • A tunnel radio system • A vehicle and incident detection system • Alterations to the Control Room of the Medway Council Control CCTV Room (Civic Centre, Strood) • Improvements to the Tunnel Offices and Control Room (West Service Building).
Background
Works and Associated Costs
3.3Tunnel Radio System
During a tunnel closure there is no effective way of communicating with personnel in the tunnel in the event of a serious incident in the tunnel and also the emergency services cannot communicate with their staff.
3.4The proposed system will provide communication to all personnel during a tunnel closure and enable the fire brigade to communicate with their staff.
3.5The cost of providing a tunnel radio system is £241,497.00
Vehicle and Incident Detection Systems
3.6At present there is a no system in the tunnel that can automatically detect incidents, smoke and unusual behaviour in the tunnel. This can be done with incident detection cameras.
3.7With the increasing safety standards in tunnels it is imperative to ensure ongoing compliance with environmental regulations. A detection system will provide confidence that a major incident of any kind can be detected promptly and reacted to.
3.8The cost of providing a vehicle and incident detection system is £242,826.50.
Alterations to the Tunnel Offices (West Service Building)
3.9The original contract called for the reuse of the existing control room and to replace all the equipment within it. During busy periods i.e. Tunnel closures it has proved very difficult to effectively manage the tunnel from such a small space.
3.10It is a now proposal to provide a larger working area for operating staff by utilising the existing ‘mess’ area which has a larger floor area and can incorporate two ‘hot desks’ for the ICT Section as part of their resilience planning. This new room can be populated, tested and commissioned without disturbing the running of the tunnel. This should prove very useful during Tunnel closures when the office is very busy. 3.11 The cost of carrying out the improvements to the West Service Building is £26,848.00.
Alterations to Medway Council CCTV Control Room (Civic Centre, Strood)
3.12During ‘out of hours’ the tunnel will be managed from the CCTV control room at the Civic Centre Strood.
3.13At the time of tender part of the control room had been designated for use as a ‘tunnel control area’. Since that time a number of changes have been made to the control room and to the personnel working in it, such that the area that had been set aside is no longer available.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.