Capital Budget Monitoring 2010/2011

Noted Executive 1 paper

Cabinet noted this item on Tuesday 29 March 2011. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

The Cabinet noted: a) The spending and funding forecasts summarised at tables 1 and 3 in the report and; b) Additions to the Capital Programme and virements as detailed in paragraph 5.1 of the report together with a further £24,323,931 in respect of the Strood Academy funded by Partnership for Schools Grant referred to in Section 4.2 of the report for which the procurement was approved by Cabinet on 15 February 2011 . 53/2011 The Cabinet agreed to formally authorise expenditure against the approved Capital Programme for 2011/2012 and future years. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Background

2.1At its meeting on the 25 February 2010, the Council approved a capital programme for 2010/2011 and future years of some £116m. Subsequent funding announcements have increased the programme to over £131 million. Details of the changes to each directorate capital programme are explained in individual commentaries in Section 4 of this report.

2.2This report consolidates the capital monitoring undertaken by each directorate, which is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.

2.3Medway Council has a capital programme for 2010/2011 now in excess of 200 individual schemes. Approximately 140 of these are principal schemes, i.e. over £100,000, including a significant number rolled forward from earlier years, and the substantial regeneration programme being progressed by Medway Renaissance. 3. Progress

3.1Table 1 below summarises the current overall expenditure and forecasts on capital schemes within each directorate for the 2010/2011 capital programme. This table summarises Appendix 1. Appendices 2 to 6 show the position by directorate.

Table 1: Spend to Date

forecast to spend Commitments to Forecast spend

Variance (is an

in later years underspend) Programme

programme Spend and 2010/2011 Approved

Approved date Directorate

£’000 £’000 £’000 £’000 £’000 Business 15,970 8,686 7,043 0 7,284 Support Dept Children & 50,405 25,477 18,683 44 24,972 Adults Regeneration, Community & 63,063 46,379 39,089 (59) 16,625 Culture Members 2,468 1,367 964 (10) 1,090 Priorities TOTAL 131,906 81,909 65,779 (25) 49,971

3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:

☺ Scheme progressing on time and within budget

Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales

Scheme neither progressing within expected timescales nor within budget.

Table 2 summarises the projects progress. Full detail is shown in the appendices: Table 2: Project Progress Summary

TOTAL Progress Monitoring ☺ SCHEMES

Business Support 19 5 0 24

Children & Adults 68 17 0 85

Regeneration, Community & Culture 64 11 1 76

Members Priorities 31 3 1 35

TOTAL 182 36 2 220 3

4. Specific Scheme Monitoring Issues and Completions 83% of schemes are progressing well, forecast to complete on time and to budget.

4.1Business Support

The BSD capital programme is a continuation of funding previously agreed, with just one increase in budget since the last report to Members, being the £29,500 increase to the Building Repairs and Maintenance Fund (BRMF) to refurbish the former Woodlands nursery as further explained in paragraph 4.2 below.

4.2Children and Adults

The directorate is reporting an overall net increase to the programme of £85,500 since the previous monitoring round, comprising of the following adjustments:

• Developer Contributions of £115,000 directed to the following projects:

- Secondary age provision at Abbey Court, Strood - £55,000; - ICT Infrastructure, St John Fisher - £60,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring 2010/2011Report 542 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, apologies
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
RC
Robin CooperOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Capital Budget Monitoring 2010/2011This decision
  2. Capital Budget Monitoring - Round 1 2026/27Noted
  3. Capital Budget Monitoring - Round 1 2026/27Noted
  4. Capital Budget Monitoring - Round 1 2026/27Noted
  5. Capital Budget Monitoring - Round 1 2026/27Noted
  6. Amendments to the Revenue Budget and Capital ProgrammeAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies