CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Medway Council
Cabinet, Tuesday 29 March 2011 at 3.00pm

Gateway 3 Procurement Tender Process Review and Contract Award: Lordswood School - Primary Amalgamation Project

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 29 March 2011. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

55/2011 The Cabinet agreed to award to B W May & Son Ltd the contract for the provision of the amalgamation project works at Lordswood School. Reasons: To provide improved accommodation to enable the school to deliver project based learning in a linked building.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission from the Cabinet to award a contract to the supplier as highlighted within section 2.5.1 of the Exempt Appendix.

This is based upon the recently undertaken procurement process for the amalgamation project works at Lordswood School. Lordswood Infant and Junior school were amalgamated in September 2010. The education vision for the headteacher, governors and senior team are to provide functional, inspirational and secure learning environments for all pupils, using the foundation stage model of open plan spaces and project-based learning.

The works will make best use of the space on the ground floor providing disabled access to all classrooms in accordance with the Equality Act 2010. The classrooms will be situated together in year groups, with access to shared resources and to outside classroom space, enabling cross class working. The new link building will join and unite the two schools physically as well as providing a functional weatherproof route for children, staff and visitors.

Cabinet approved the commencement and delivery of this procurement requirement at Procurement Gateway 1 on 21 December 2010.

This Procurement Gateway 3 Report has been approved for submission to the Cabinet after review and discussion by Children and Adults Directorate Management Team and consideration at the Strategic Procurement Board on 9 March 2011. The Children and Adults Directorate Management Team and Strategic Procurement Board have recommended that this procurement project be approved as a Category B High Risk procurement project at Procurement Gateway 1 by Cabinet. This is because although this procurement project is Works Category B Medium Risk procurement with a total contract value above £250,000.00, a new project appraisals process was agreed by Cabinet on 28 September 2010 (decision number: 142/2010) that all Children’s Services Capital projects for schools over £500,000 would be considered by Cabinet.

1. Budget and Policy Framework

1.1Contract Award Decision

1.1.1 The decision to award a contract to the supplier as highlighted within section 2.5.1 of the Exempt Appendix for this procurement requirement is within the Council’s policy and budget framework and ties in with all the identified Core Values, Strategic Priorities, Strategic Council Obligations and Departmental/Directorate service plans as highlighted within the Gateway 1 Report to Cabinet on 21 December 2010. 2. Background

2.1Permission Required from the Cabinet

2.1.1 This Procurement Gateway 3 Report asks the Cabinet to award a contract to the supplier as highlighted within 2.5.1 of the Exempt Appendix.

2.1.2 This is based upon the recently undertaken procurement using a mini- competition to select five contractors from KCC’s select list of approved contractors. The competition was established to procure a single stage tender on specification and drawings with a standard JCT contract. The design team fully specified the build solution prior to inviting tenders. This enabled greater certainty on cost, as the design is not likely to vary post-tender unless something unforeseen occurs and this will be managed via the formal contractual variation process.

2.2Contract Details

2.2.1 Procurement type

The proposed award of a contract to the supplier as highlighted within section 2.5.1 of the Exempt Appendix relates to a Construction procurement requirement.

2.2.2 Contract duration

The contract duration for this procurement requirement is 21 weeks and there are no provisions within the contract to extend. The contract is proposed to commence on 11 April 2011. 2.2.3 Contract value

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Procurement Tender Process Review and Contract Award: Lordswood School: Primary Amalgamation ProjectReport 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, apologies
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
RC
Robin CooperOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Procurement Tender Process Review and Contract Award: Lordswood School - Primary Amalgamation ProjectThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayAgreed
  5. Gateway 1 Procurement Commencement: Innovation Park Medway NorthAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies