21/2013 The Cabinet approved the procurement contract award to Strode Park Foundation. 22/2013 The Cabinet agreed to delegate authority to the Assistant Director of Legal and Corporate Services in consultation with the Finance Portfolio Holder to grant a lease of Platters Farm Lodge for up to 25 years. Reasons: The outsourcing of this service will provide best value because the contract award price is below unit cost for comparable services, (Unit Costs of Health and Social Care, PSSRU, University of Kent 2011) for rehabilitation & respite (intermediate care). The recommended supplier has demonstrated an ability to maintain the quality of the service and innovate service development and improvement.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1.1 This Procurement Gateway 3 Report seeks permission from the Procurement Board to award a contract to the supplier as highlighted within 2.5.1 of the Exempt Appendix.
2.1.2 This is based upon the recently undertaken procurement process of outsourcing the three Linked Service Centres.
2.2Contract Details
2.2.1 Procurement type
The proposed award of the contract to the supplier as highlighted within 2.5.1 of the Exempt Appendix relates to a Services contract.
2.2.2 Contract duration
The contract is for two services: respite and rehabilitation care and day care services.
The contract duration for this procurement requirement in relation to respite and rehabilitation is 25 years with a 5-yearly break clause and there are no provisions within the contract to extend.
The contract duration for this procurement requirement in relation to day care is 3 years with an option to extend for a further 2 years. The contract for respite and rehabilitation is proposed to commence on 1 April 2013 and conclude on 31 March 2038. The contract for day care is proposed to commence on 1 April 2013 and conclude on 31 March 2016.
2.2.3 Contract value
The total contract value associated with this contract is £32,931,600.
2.3Procurement Tendering Process
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.