216/2013 The Cabinet approved the contract award to install a wireless network solution for the Hoo Peninsula to MLL Telecoms, as outlined within section 2.2 of the Exempt Appendix . Reasons: The current network solution on the Hoo Peninsula was not fit for purpose and was inhibiting the delivery of high quality education for young people who learn there. The procurement would provide an upgradable cost effective solution.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to award a contract to the supplier as highlighted within Section 3.2 of the Exempt Appendix.
The Cabinet approved the commencement of this requirement at Gateway 1 on 1 October 2013, following consideration by Procurement Board on 17 September 2013. A copy of the Gateway 1 Report is available upon request.
This Gateway 3 Report has been approved for submission to the Cabinet after review by Directorate Management Team on 29 November 2013 and Procurement Board on 4 December 2013.
1. Budget and Policy Framework
1.1This procurement is within Budget and is consistent with the Policy Framework. The proposals support the Council’s priorities as set out within the Medway Council Plan, specifically the core value of providing value for money and the commitment that the council will champion strong leadership and high standards in schools; so that all children can achieve their potential, and the gaps between the least advantaged and their peers are narrowed. This procurement will also support the strategic priorities set out in the Children and Young People’s Plan, such as the priority to raise the aspirations and expectations for all children, families, teachers, schools and communities in Medway. 2. Background
2.1Medway Council is seeking to procure a resilient managed wide area network service, based on microwave radio, for potentially 18 sites on the Hoo Peninsula. As an organisation Medway Council has a responsibility to provide schools purchasing ICT services from the council, a fit for purpose network. The Hoo Peninsula suffers from a lack of traditional connectivity and so the Council commissioned a review for a wireless based solution. After an in depth study, Medway Council have concluded that the optimal way of delivering a faster, more reliable network to the area is to adopt the use of microwave radio. The Council has sought to ensure best value and have included a number of corporate sites in the design.
2.2Funding/Engagement from External Sources
Medway Grid for Learning (MGfL) ring fenced capital for the installation and MGfL revenue for the yearly rental.
2.3Urgency of Report
This procurement is urgent to meet the need to start implementation in January 2014 and to improve the present poor connectivity that is affecting teaching and learning at these sites.
3. Procurement Process
3.1Procurement Process Undertaken
The procurement has followed the mini competition tendering process and has used the FAB-Telecoms-12 Fabrick Housing Group Framework. The selection list has been taken from this framework where two suppliers showed an interest in tendering. Medway has also followed a consultation process with schools.
3.2Evaluation Criteria
The quality and cost ratio used for the procurement was 60%/40%.
There were four sub criteria for quality; Managing Construction, Network Delivery, Customer Service and References. Quality: 60% Contractor A Contractor B Contractor C Score (out Weighted Score Weighted Score Weighted Criteria Weighting of 5) Score (out of 5) Score (out of 5) Score A: Managing Construction 1: Network Solution (A1) 6% 2: Installation and CDM (A2) 6% 3: Maintenance & Relocation (A3) 5% 4: Error procedures (A4) 3% 5: Completion time-scales (A5) 4% B: Network Delivery 1: Network carrier only 5% service (B1) 2: IL2 and 99.85% availability (B2) 4% 3: Bandwidth guarantee (B3) 8% 4: Network services (B4) 3% 5: Future upgrades (B5) 3% C: Customer Service & support 1: Customer and stakeholder liaison 3% 2: Support 5% D: References
1: References 5% Total Weighted Score % 60% 4. Business Case
4.1Delivery of Procurement Project Outputs / Outcomes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.