50/2014 The Cabinet agreed to the award of the contract to Bolt & Heeks for the Phase 1 Works at Brompton Westbrook Primary School. Reasons: The Council has a statutory duty to ensure there are sufficient school places as set out in the Education & Inspections Act 2006 and t his project supports the Council’s School Organisation Plan 2011 – 2016, which highlights the need for additional pupil places in Gillingham. The new accommodation will also allow the school to increase the use of the schools facilities by the local community. The Procurement process was carried out in line with the Council’s Contract Rules and that best value for money has been delivered through this process .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to award a contract to the supplier as highlighted within Section 2.2 of the exempt appendix.
The Cabinet approved the commencement of this requirement at Gateway 1 on 1 October 2013. A copy of the Gateway 1 Report is available upon request.
This Gateway 3 Report has been approved for submission to the Cabinet after review and discussion at the Children and Adults Directorate Management Team Meeting on 21 January 2014 and Procurement Board on 22 January 2014.
1. BACKGROUND INFORMATION
1.1Budget & Policy Framework
1.2This project supports the Council’s School Organisation Plan 2011 – 2016, approved by Cabinet on 1 November 2011 (decision number 142/2011), which highlights the need for additional pupil places in Gillingham. The Council has a statutory duty to ensure there are sufficient school places as set out in the Education & Inspections Act 2006.
1.3A budget has been identified to provide the additional accommodation required to increase the planned admission number to 60. A feasibility study has been undertaken that has highlighted the shortfall in the current accommodation, in line with the DfE Building Bulletin 99 guidance. 1.4 The new accommodation includes a school/community hall with changing facilities, a new main entrance, two new classrooms and additional dining space. This allows the existing hall to be used as SEN group rooms and for pastoral care. It also allows reconfiguration of the office spaces, which are currently undersized and not optimally located.
1.5The new accommodation will allow the school to increase the use of the schools facilities by the local community. The arrangement of the existing hall, in the centre of the building, severely limits these opportunities for security reasons.
1.6Background Information
1.7This procurement is a Works/Construction project.
1.8This report seeks permission from Cabinet to award a contract to the supplier as highlighted in the exempt appendix for the main contract works for September 2014. Following the detailed design work it was identified that due to budget pressures that non-critical items would need to be completed as a separate phase but due to the submission from this contractor this will not be necessary as the works can now be completed in one phase.
1.9This project is required to fulfil Medway’s statutory obligations. The Council has a statutory duty to ensure there are sufficient school places as set out in the Education & Inspections Act 2006.
1.10Funding/Engagement from External Sources
1.11As the Targeted Funding bid made to the DfE in respect of this project was unsuccessful, funding will be provided from the DfE Basic Need Grant and Developer Contributions. No external approval is required for this project to proceed.
2. PROCUREMENT PROCESS
2.1Procurement Process Undertaken
2.2This project is a single stage Design and Build tender via the Kent County Council Select List.
2.3The advert went out on the ProContract website to 6 Contractors from the KCC Select List and we received 5 Tender submissions on 13 December. 2.4 Out of the 5 Tenders received, one withdrew from the competition. Once the evaluation had been completed from the 4 contractors, Contractor C’s submission was accepted as the winning bidder. 2.5 Evaluation Criteria 2.6 The evaluation criteria were based on a 60% Quality/40% Price ratio - see matrix within the exempt appendix. 3. BUSINESS CASE
3.1Delivery of Procurement Project Outputs / Outcomes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.