89/2015 The Cabinet approved the procurement of one or more consultants for design and contractors for construction of the projects outlined in the report in order to successfully deliver the Local Growth Fund programme, as follows: Cycle A ction Plan project – Traditional procurement approach Strood Town Centre project – Traditional procurement approach Medway City Estate project – Traditional procurement approach A289 Four Elms roundabout project – Procurement options report to be presented to a future meeting . Reasons: The decision to commence procurement of the necessary design consultation for each project will allow officers to commence the delivery of each project. A delay in the ability to procure the required design consultancy and construction delivery will have a negative impact on the Council’s ability to deliver these Local Growth Fund projects .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to commence the procurement of one or more contractors, and consultant design teams as required, to deliver four projects within the Local Growth Fund program. These projects are:
A289 Four Elms Roundabout to Medway Tunnel improvements Strood town centre journey time improvements Medway City Estate connectivity improvements Medway Cycling Action Plan
This Gateway 1 report has been approved for submission to the Procurement Board after virtual review and discussion by those appropriate officers of the Regeneration Community and Culture Directorate Management Team (DMT).
The Regeneration Community and Culture DMT has recommended that the projects included in the programme be approved as Category B high-risk procurements.
There a range of political and service sensitivities regarding the delivery of these projects and the scope and achievability of the desired outcomes. These issues will be addressed and appropriately managed through the delivery of each individual project.
1. BACKGROUND INFORMATION
1.1Budget & Policy Framework
1.1.1 These projects will be funded from the Local Growth Fund (LGF). Initial funding bids for these projects were submitted in early 2014. Following significant work on the subsequent Outline Business Cases for the five proposed projects, the South East Local Enterprise Partnership (SE LEP) confirmed in March 2015 that Medway had successfully secured LGF Round 1 funding of £28.6 million for the five projects. The SE LEP have provided a funds release schedule which officers will incorporate in to the project management of each scheme.
1.2Service Background Information
1.2.1 The four projects covered by the scope of this report are:
Project Title Scope of Project Estimated Completion Start of Construction A289 Four Elms Journey time and network Oct 2017 Dec 2018 Roundabout to improvements Medway Tunnel Strood Town Journey time improvements and April 2017 June 2018 Centre accessibility enhancements in Strood town centre Medway City Medway City Estate connectivity April 2017 March 2018 Estate improvement measures Medway Package of measures to April 2016 March 2018 Cycling Action improve to cycle network and Plan cycle hub facilities in Medway
1.2.2 The fifth project, Chatham Town Centre place making and public realm improvement package, was previously presented to the Procurement Board on 5 November 2014. The recommendation agreed was to commence procurement of two separate contracts, one for design consultation to produce a high level master plan for the Chatham project, and the second for a contractor to deliver the works. LGF funding for this project amounts to £4.0m.
1.2.3 Similarly, this report recommends the commencement of necessary procurement of design consultation and works delivery for the four projects outlined above.
1.3Project Details
1.3.1 These projects link closely to all the five priorities set out in Medway’s Local Transport Plan (LTP) 2011/2026:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.