Gateway 1 Procurement Commencement: Local Growth Fund Programme

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 June 2015. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

89/2015 The Cabinet approved the procurement of one or more consultants for design and contractors for construction of the projects outlined in the report in order to successfully deliver the Local Growth Fund programme, as follows: Cycle A ction Plan project – Traditional procurement approach Strood Town Centre project – Traditional procurement approach Medway City Estate project – Traditional procurement approach A289 Four Elms roundabout project – Procurement options report to be presented to a future meeting . Reasons: The decision to commence procurement of the necessary design consultation for each project will allow officers to commence the delivery of each project. A delay in the ability to procure the required design consultancy and construction delivery will have a negative impact on the Council’s ability to deliver these Local Growth Fund projects .
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission to commence the procurement of one or more contractors, and consultant design teams as required, to deliver four projects within the Local Growth Fund program. These projects are:

 A289 Four Elms Roundabout to Medway Tunnel improvements  Strood town centre journey time improvements  Medway City Estate connectivity improvements  Medway Cycling Action Plan

This Gateway 1 report has been approved for submission to the Procurement Board after virtual review and discussion by those appropriate officers of the Regeneration Community and Culture Directorate Management Team (DMT).

The Regeneration Community and Culture DMT has recommended that the projects included in the programme be approved as Category B high-risk procurements.

There a range of political and service sensitivities regarding the delivery of these projects and the scope and achievability of the desired outcomes. These issues will be addressed and appropriately managed through the delivery of each individual project.

1. BACKGROUND INFORMATION

1.1Budget & Policy Framework

1.1.1 These projects will be funded from the Local Growth Fund (LGF). Initial funding bids for these projects were submitted in early 2014. Following significant work on the subsequent Outline Business Cases for the five proposed projects, the South East Local Enterprise Partnership (SE LEP) confirmed in March 2015 that Medway had successfully secured LGF Round 1 funding of £28.6 million for the five projects. The SE LEP have provided a funds release schedule which officers will incorporate in to the project management of each scheme.

1.2Service Background Information

1.2.1 The four projects covered by the scope of this report are:

Project Title Scope of Project Estimated Completion Start of Construction A289 Four Elms Journey time and network Oct 2017 Dec 2018 Roundabout to improvements Medway Tunnel Strood Town Journey time improvements and April 2017 June 2018 Centre accessibility enhancements in Strood town centre Medway City Medway City Estate connectivity April 2017 March 2018 Estate improvement measures Medway Package of measures to April 2016 March 2018 Cycling Action improve to cycle network and Plan cycle hub facilities in Medway

1.2.2 The fifth project, Chatham Town Centre place making and public realm improvement package, was previously presented to the Procurement Board on 5 November 2014. The recommendation agreed was to commence procurement of two separate contracts, one for design consultation to produce a high level master plan for the Chatham project, and the second for a contractor to deliver the works. LGF funding for this project amounts to £4.0m.

1.2.3 Similarly, this report recommends the commencement of necessary procurement of design consultation and works delivery for the four projects outlined above.

1.3Project Details

1.3.1 These projects link closely to all the five priorities set out in Medway’s Local Transport Plan (LTP) 2011/2026:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Procurement Commencement: Local Growth Fund ProgrammeReport 116 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
AJ
Councillor Alan Jarrett (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
RC
Councillor Rodney Chambers, OBE (Con)Committee Member, apologies
JC
Councillor Jane Chitty (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
AG
Councillor Adrian Gulvin (Con)Committee Member, present
AM
Councillor Andrew Mackness (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
RT
Councillor Rupert Turpin (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
AB
Dr Alison BarnettOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Gateway 1 Procurement Commencement: Local Growth Fund ProgrammeThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayAgreed
  5. Gateway 1 Procurement Commencement: Innovation Park Medway NorthAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies