207/2014 The Cabinet approved the contract award to carry out the conservation works at Eastgate House to Fairhurst Ward and Abbott Limited, as set out in paragraph 3.2 of the exempt appendix, and achieving the outputs and opportunities described in paragraph 3 of the report. Reasons: The project will conserve this wonderful building and heritage for generations to come opening it up as a distinctive, valued and vibrant community resource for Medway and our visitors.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to award a contract to the supplier(s) as highlighted within Section 3.2 of the Exempt Appendix.
The Cabinet approved the commencement of this requirement at Gateway 1 on 29 October 2013.
This Gateway 3 Report has been approved for submission to the Cabinet after review and discussion at the Regeneration Community and Culture Directorate Management Team Meeting on 24 November 2014 and Procurement Board on 3 December 2014.
1. BACKGROUND INFORMATION
1.1Budget & Policy Framework
1.1.1 This project is named specifically on the Medway Council Plan:
Eastgate House improvements The project focuses on conserving the important historic fabric of Eastgate House and adapting the building so that it can be used as a distinctive and vibrant community resource for Medway residents and our visitors.
Departmental and Directorate Service Plans This project links into the following Departmental/Directorate Service Plans through: Medway Destination Management Plan The Medway Cultural Strategy 2014-2019. 1.2 Background Information
1.2.1 The project will conserve this wonderful building and heritage for generations to come opening it up as a distinctive, valued and vibrant community resource for Medway and our visitors. When completed, the project will have transformed access to and experience of this much loved local landmark creating a sustainable future for Eastgate House.
1.2.2 An exciting and diverse range of activities and interpretation, inspired by the building and its residents over 400 years will enable anyone living in or visiting Medway to learn about, experience and enjoy this unique heritage.
1.2.3 Addressing the urgent conservation requirements of the house will transform this Tudor mansion and secure the future of the building.
1.2.4 A new lift, sensitively designed to complement the site, and the reinstatement of a demolished staircase will allow access for all to floors closed for decades. A robust Conservation Management Plan will ensure that decisions throughout the project and beyond are taken with full consideration and understanding of the historical, social, aesthetic and communal significance of all areas of the house.
1.2.5 The project will introduce new galleries and education spaces to facilitate our learning and participation aims. Significant improvements to visitor facilities will generation new opportunities for income generation, creating new jobs and ensuring sustainability of the project.
1.3Funding/Engagement from External Sources
1.3.1 As this project encompasses funding from external sources, authority to proceed with this procurement direction has been reviewed and approved by the Heritage Lottery Fund.
2. PROCUREMENT PROCESS
2.1Procurement Process Undertaken
2.1.1 The procurement process followed a restricted procedure (non-OJEU) via the Kent Business Portal, in line with the Council’s Contract Procedure Rules.
2.1.2 The PQQ was published on the portal on 9 July and 15 submissions were returned on 1 August. 44 contractors originally expressed an interest in the opportunity. The main reasons for the low response were contractors’ existing workload being too high and the size of the project not being suitable.
2.1.3 Following evaluation of the PQQ, 6 contractors were shortlisted and invited to proceed to submit a full tender on 1 September. 2.1.4 5 bids were received on 30 October.
2.1.5 The content of the PQQ and the ITT, as well as the final shortlist of contractors was agreed with the Heritage Lottery prior to publication.
2.1.6 The Heritage Lottery fund approved the selection of the preferred contractor at a meeting on 18 November 2014, when the final evaluation was presented to them.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.