Gateway 3 Contract Award: Rochester Riverside Regeneration

Approved Executive 1 paper

Cabinet approved this item on Tuesday 8 March 2016. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

51/2016 The Cabinet approved the award of the contract, or series of contracts for Rochester Riverside Regeneration to Countryside subject to HCA approval on 10 March 2016, and achieving the outputs described in Section 3 of the report. The Cabinet noted that a report will be submitted to Full Council for information on 28 April 2016 detailing this land and property transaction over £500,000 in accordance with the Constitution.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report requests the Cabinet to approve the procurement of a sole development partner with a contract, or series of contracts to ensure sufficient time to deliver the regeneration of Rochester Riverside, which is anticipated to take between 10 to 15 years, as highlighted within 3.2 of the Exempt Appendix. This will involve a development agreement to ensure a quality development as well as the freehold transfer of the site in phases throughout the development period.

This is based upon the previous legal advice that stated that the procurement should be for a sole development partner to be sourced via the EU Competitive Negotiated Procedure. This process that has included the Invitation to Negotiate (ITN) Phase reduced the initial tenders from five to three, then the Invitation to Continue Negotiations (ITCN) Phase reduced the tenders from three to two and then the Best and Final Offers (BAFO) Phase which saw the receipt and evaluation of the final two tenders.

Cabinet approved the commencement and delivery of this procurement requirement at Gateway 1 on 2 December 2014, decision number 195/2014.

This Procurement Gateway 3 Report has been approved for submission to the Cabinet after review and discussion at Regeneration, Community and Culture Directorate Management Team meeting on 7 January 2016, the Rochester Riverside Board on 12 January 2016 and the Procurement Board on 17 February 2016. The Homes and Communities Agency (HCA), the Council’s partners for this development, is also required to approve the procurement of a sole development partner with a contract, or series of contracts.

1. BACKGROUND INFORMATION

1.1Budget & Policy Framework

1.1.1 Rochester Riverside is designated as an Action Area for redevelopment in the Medway Local Plan (2003). Policy S7 of the Local Plan states that the comprehensive regeneration of the area will be sought in accordance with a development brief as approved by the Council.

1.1.2 In September 2014 Cabinet approved the adoption of the 2014 Rochester Riverside Development Brief and Masterplan as a Supplementary Planning Document to the Local Plan. The Development Brief establishes a set of strategic parameters and illustrative guidance to steer the future development of the site, provides planning and design guidance to Developers, and will inform future development management decisions.

1.1.3 This matter will be reported to Full Council for information on 28 April 2016 in accordance with the constitutional requirement that land and property transactions over £500,000 be reported to the next Council meeting for information.

1.2Background Information

1.2.1 Rochester Riverside is a 32-hectare (74-acre) flagship regeneration scheme within the Thames Gateway. The site stretches from the A2 Rochester Bridge southwards to Doust Way, with the River Medway forming the eastern boundary of the site, and the high-speed rail line to central London forming the western boundary.

1.2.2 The scheme is managed in partnership by Medway Council and the Homes and Communities Agency (HCA), who jointly own the site and have invested substantial funds in land assembly, remediation, site preparation and infrastructure works to enable the comprehensive regeneration of the site. Representatives of each partner sit on the Rochester Riverside Board.

1.2.3 The key objective of the partners is to transform the area into an attractive place to live, work and play through the implementation of a substantial, high quality, sustainable, mixed use scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: Rochester Riverside RegenerationReport 59 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
AJ
Councillor Alan Jarrett (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
RC
Councillor Rodney Chambers, OBE (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
AG
Councillor Adrian Gulvin (Con)Committee Member, apologies
AM
Councillor Andrew Mackness (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
RT
Councillor Rupert Turpin (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
AB
Dr Andrew BurnettOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contract Award: Rochester Riverside RegenerationThis decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies