41/2021 The Cabinet approved progressing of the re-development proposal outlined at Exempt Appendix 1, including the RIBA stage 2 design works. Reasons: The Council wants to regenerate Chatham and wants to support the economic renewal post Covid-19 of the “city centre” of Medway. By progressing this proposal the Council will be working towards its ambitions for a more vibrant and busy Pentagon Centre.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report provides Cabinet with an update on the proposed re-development of the Pentagon Centre.
1. Budget and policy framework
1.1Decisions about the Council’s property portfolio are a matter for Cabinet.
2. Background 2.1. The Cabinet approved the acquisition of the Pentagon Centre on 12 February 2019 (decision no. 31/2019) after taking professional advice from industry experts Knight Frank, with Council agreeing to the funding of the purchase and investment in the Centre on 21 February 2019 for a total sum of up to £45 million (minute no. 838/2019). Under delegated authority, officers completed the buying of the Pentagon Centre head leases together with some freehold properties in April 2019 for £34.875 million. A reduction of almost £1million was achieved just prior to completion.
2.2Cabinet received an update report in July 2019 which advised Members that Ownership of a significant asset such as the Pentagon Centre allowed the Council to consider how else it might intervene to encourage vitality and economic growth in Chatham. This followed, at that time, significant investment in the public realm from Chatham Station, by St John’s Church down through Military Road and onto the Paddock area in central Chatham. It also followed the Council, through its housing company, MDC, achieving planning permission for residential schemes at sites now known as Garrison Point and Waterfront Chatham in close proximity to the Pentagon Centre. The development of those residential sites are now both well underway.
2.3To that list of activity reported to Cabinet can now be added a series of other interventions. A planning application has now been submitted for 161 units at Mountbatten House, with the newbuild element of that scheme including a food and beverage offer and improvements to the public realm area just opposite the Brook Theatre (see computer generated image below). That planning application is due to be heard at the Council’s Planning Committee meeting in April. Consideration will also take place of a linked affordable housing scheme for 24 units on the site of the current Upper Mount car park site.
Fig1 CGI of Plaza area opposite the Brook Theatre used in the public consultation process
2.4The Council has worked as part of a joint venture with Creval who are bringing forward a planning application for 178 units at Queen Street and 45 units of affordable housing on an adjacent site. (Decision 164-166/2020 refers).
2.5The Council has also been notified that it is likely to receive £9.6 million through the Future High Streets Fund which will enable some of the proposed re-development proposals.
2.6Members were advised that Officers would in the first instance seek general advice on the various options open to the Council for the Pentagon site, so that they these can be appraised and presented to Members. That work has now taken place. The first element of proposed development is set out in detail in the attached Exempt appendix 1.
3. Redevelopment proposals 3.1. The Council is in advanced discussions with a public sector organisation to reconfigure and occupy an area of the Centre. The envisaged project would provide the prospective tenant with the ability to divest itself of other unsuitable property, it would provide a rental income to the Council. It would drive footfall to the centre and improve the overall vitality of this strategic asset. This proposal would dovetail well with the bringing back into use of Mountbatten House and the other town centre improvements planned to be delivered over the next 2-3 years, set out above.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.