CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Medway Council
Cabinet, Tuesday 7 June 2022 at 3.00pm

Gateway 3 Contract Award - Recycling Resource Management Contract

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 7 June 2022. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

82/2022 The Cabinet agreed to award the contract to: - Lot 1 – Veolia Environmental Services - Lot 2 – Veolia Environmental Services as they had been evaluated as the most economically advantageous against the Council’s award criteria as per the evaluation spreadsheet contained within 3.1 of the Exempt Appendix.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report requests the Cabinet’s agreement to award the procurement of the Recycling Resource Management Contract (Oct 2022).

Procurement Overview Total Contract Value: £4,470M Project Budget: £6,698M

Contract Term: 48 months (24 Month + 24 Month extension)

1. Budget and Policy Framework 1.1. This procurement board report is within the Council’s policy and budget framework and ties in with all the identified Core Values, Strategic Priorities, Strategic Council obligations and Departmental/Directorate service plans.

2. Background Information and Procurement Deliverables 2.1. The current Recycling Resource Management contract was entered into via a VEAT notice with Veolia and commenced 01/10/2019 for an initial term of two-years with a further one-year extension (three-years total until 30/09/2022). 2.2. The services this contract relates to include:

2.2.1. Provision of a transfer station (for clarification, a transfer facility is a key piece of waste infrastructure where waste is delivered for bulking and onward transportation).

2.2.2. Haulage and treatment of: 2.2.2.1. Kerbside recycling (container mix and fibre) 2.2.2.2. Ancillary recycling (such as bring sites)

2.2.3. Transfer only of: 2.2.3.1. Organic waste

2.3Under the current contracted arrangement, the services detailed in 2.2.2. are delivered through the Veolia owned and operated transfer station at Whitewall Road, Strood.

2.4Currently Medway Council take full risk on the recyclate material prices as dictated by the market conditions at the time. This means that materials that produce an income are offset against the total contract costs payable by Medway Council and conversely that any material that costs for disposal falls to Medway to pay full price.

2.5Over the three-year life of the current contract (01/10/19 – 30/09/22) an estimated 194,000 tonnes of recycling will have been processed at an estimated cost of £4.7M.

2.6Proposed contracted services:

2.6.1. The new contract was advertised in two lots as follows:

2.6.1.1. Lot 1 – Transfer station and haulage

2.6.1.2. Lot 2 – Recycling treatment

2.6.2. The successful bidder for Lot 1 and Lot 2 services will provide a solution of up to four-years which meets Medway’s requirements as detailed in 1.2.2 and complies with statutory duties.

2.6.3. Market engagement was undertaken prior to the tendering process to ensure that Medway had hit the right tone for current market conditions.

2.6.4. The proposed contract will see Medway share risk on the recyclate material prices as dictated by the market conditions based on an 80/20 split (Medway/Bidder). This is more favourable than the 100% risk share that currently sit with Medway.

2.6.5. The proposed contract includes a new mechanism for Lot 1 services where the bidder can recharge Medway for rejected and contaminated waste loads. This is a standard clause common in waste contracts and presents a risk for the residual waste budget. However, it is important to highlight that this risk is lowered as a result of: 2.6.5.1. Clear Medway Norse procedures in terms of collection method, including financial penalties for Medway Norse if contamination is high.

2.6.5.2. Strong Lot 1 contract clauses relating to waste acceptance procedures

2.6.6. The proposed contract will be for up to four-years (as opposed to the previous three-year contract) processing an estimated 265,000 tonnes of recycling throughout its life at an estimated cost of £5M based on the contractors bid.

2.7Parent Company Guarantee/Performance Bond Required

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: Recycling Resource Management ContractReport 201 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
AJ
Councillor Alan Jarrett (Con)Committee Member, apologies
HD
Councillor Howard Doe (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
RC
Councillor Rodney Chambers, OBE (Con)Committee Member, apologies
JC
Councillor Jane Chitty (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
AG
Councillor Adrian Gulvin (Con)Committee Member, present
GH
Councillor Gary Hackwell (Con)Committee Member, present
MJ
Councillor Mrs Josie Iles (Con)Committee Member, present
MP
Councillor Martin Potter (Con)Committee Member, present
MT
Michael TurnerCommittee Co-ordinator, expected

On this subject at Medway

Search all
  1. Gateway 3 Contract Award - Recycling Resource Management ContractThis decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies