Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet agreed to pursue competitive procurement of Housing Related Support Services as per preferred option 4
Money£5.53milPotential additional cost to temporary accommodation if all 181 current residents required alternative housing over the life of the contract
What happens nextTender publication autumn 2026Contract start date 01 April 2027, with mobilisation from January to March 2027
Who it affects181 vulnerable peopleCurrently housed residents including young people, ex-offenders, homeless people with support needs and domestic abuse victims
What was decided
The Cabinet agreed to pursue the procurement of Housing Related Support Services as per the preferred option 4 identified in paragraph 7.2.5 of the report. Report P2
Why
The current contract extension comes to conclusion on 31 March 2027, and a procurement exercise is required to ensure Medway can provide commissioned supported housing for vulnerable residents. Report 2.1
Without procurement, providers would evict people from accommodation and potentially reuse it for other purposes, causing an immediate increase in people presenting as homeless and increasing demand on temporary accommodation or adult social care placements.
The service carries out a preventative function which aligns with the Medway Homelessness Prevention and Rough Sleeping Strategy to 2030 and the National Plan to End Homelessness.
What happens next
Tender publication to advertise the opportunity to the market, with evaluation, standstill period and contract award to follow. Report P47, P48, P49, P50, P51, P52
Mobilisation period from January to March 2027, with the new contract commencing on 01 April 2027. Report P53, P54
Approval of additional funding is dependent upon Full Council's approval of the 2027/28 budget in February 2027. Report P80
The money
£5.53mil Potential additional cost to temporary accommodation if all 181 current residents required alternative housing over the life of the contract Report 2.3, P61
Options considered
Rejected: Option 1, Do nothing. Providers would evict people from accommodation and there would be an immediate increase in people presenting as homeless
Rejected: Option 2, Extend the current contract. Contract extensions end on 31 March 2027 with no further available extensions
Rejected: Option 3, Utilise a framework or existing contract. No current framework exists
Chosen: Option 4, Competitive procurement. Preferred route although concerns about the market have been noted
Implications
Financial: Additional budget provision has been incorporated into the Medium Term Financial Outlook, subject to Full Council approval of the 2027/28 budget in February 2027 Report P80
Legal: Housing Related Support Services contribute to Medway Council's legal duty to prevent homelessness under the Homelessness Reduction Act 2017 and the Housing Act 1996
Risk: Little competitive market at the current price point; providers have not committed to bid at current contract values and there is a risk of insufficient service capacity Report P69, P70
Other: All lots within the contract will have staff eligible for TUPE transfer Report P84
Who and where
181 vulnerable people currently housed through these schemes Report 2.3, P61
Providers of current services Report P38
Dartford and Gravesham management teams as potential new North Kent authority partners Report P71
Timeline
February 2027: Full Council approval of 2027/28 budget Report P80
January to March 2027: Mobilisation period Report P53
31 March 2027: Current contract ends Report P15, 2.1
Housing Related Support Services: Supported housing for vulnerable people who may not be deemed in priority housing need, providing person-centred support to develop independent living skills
TUPE: Transfer of Undertakings (Protection of Employment) Regulations - protects employees when a business transfers to a new owner
MQAF: Medway Quality Assurance Framework - the standard against which quality of support and accommodation will be audited
SMART targets: Specific, Measurable, Achievable, Relevant, Time-bound targets within support plans
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
148/2026 The Cabinet agreed to pursue the procurement of Housing Related Support Services (Supported Housing, typically for vulnerable cohorts within Medway’s population who may not be deemed in priority housing need), as per the preferred option 4 identified in paragraph 7.2.5 of the report.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to commence the re-procurement of the Housing Related Support Services contract.
1. Recommendation 1.1. The Cabinet is asked to agree to pursue the procurement of Housing Related Support Services (Supported Housing, typically for vulnerable cohorts within Medway’s population who may not be deemed in priority housing need), as per the preferred option 4 identified in paragraph 7.2.5 of the report.
2. Suggested reasons for decision
2.1The recommendation is made on the basis that the previous Housing Related Support Services were commissioned in 2021 and ran from April 2022. The contract extension comes to conclusion on 31 March 2027, and to ensure that Medway is able to provide commissioned supported housing for vulnerable residents, a procurement exercise is required to commence in autumn 2026.
2.2Medway has a range of supported housing which ranges from services which provide a statutory duty (housing related support for people fleeing domestic abuse, as per the Domestic Abuse Act 2021, to those who may not meet thresholds for homelessness or adult social care provision at point of entry into services but are deemed to be vulnerable and at risk of meeting thresholds if action is not taken to prevent escalation of need.
2.3There are currently 181 people being housed and supported through these schemes which are in most cases more cost effective than would be the case if they were housed through statutory channels such as temporary accommodation. If all current residents of supported accommodation required temporary accommodation this could result in an additional cost of approx. £5.53mil (over the life contract) to temporary accommodation.
2.4Should the contract end without further procurement activity, this would cause significant burden on Housing Services to provide alternative accommodation for those currently residing in supported accommodation. Loss of this service creates an ongoing additional barrier for single people moving out of temporary accommodation.
3. Budget & Policy Framework
3.1The procurement aligns with Medway’s Homelessness Prevention and Rough Sleeping Strategy to 2030 with regards to addressing homelessness and rough sleeping, the One Medway Council Plan with regards to suitable accommodation to meet resident needs and the People Strategy with regards to high quality of support for people who need it, and the Kent and Medway Domestic Abuse Strategy. With regards to wider determinants of health, these services are significant contributors to Medway’s Marmot Place objectives, with support plans including goals around developing better outcomes in health, education, employment and a variety of independent living skills. In terms of the national picture, the National Plan to End Homelessness (Dec 2025) is clear on the necessity to provide high quality supported housing to prevent people sleeping rough and to accommodate those with a level of immediate need which cannot be effectively supported in independent living.
4. Background Information and Procurement Deliverables
4.1Background Information
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.