RESOLVED 1. Cabinet notes the current position on demand and supply of school places and agrees the contents of this report as the council’s current school places strategy, and specifically: 2. That the council reviews the position on specific supply and demand of primary school places over the next 18 months and beyond before committing to any further expansion in permanent accommodation beyond the 21 forms of entry increase already being progressed 3. That officers progress the direction of travel for secondary and special school expansion outlined in paragraphs 2.26 and 2.30 of the report.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Provision of school places report – update and future strategy
Appendix 1 - Primary School provision
TABLE 1‐ ACTUAL AND GLAs FORECAST ROLL AGAINST ADMISSION NUMBERS INCLUDING PLANNED INCREASES Extra FEs required Actual above 21FE Total roll/GLA planned, admissi Cumulative Standard Surplus/Deficit with 2% Zero on extra PAN projection (‐) against PAN surplus develop Alternate number since published (No allowance allowance ment model (PAN) 2007/08 Spring '12 for 2% surplus) forecast forecast
Notes “FE” is a form of entry – 30 places per year “PAN” is published admission number. Column 2 is the total of all school PANs for LB Merton primary schools
We are seeking to provide a 2% surplus (i.e. approximately 60 places) so ideally the surplus in 5th column above should be around 60. The 6th column therefore shows the FEs required after allowing for the 2% surplus i.e. 60 places/2FE.
Park Community “Free” School is planned to open in September 2014 on the LB Merton/RB Kingston borders and provide 60 places per year (2FE). This will be above the 2640 places stated
It should be noted that based on admissions information for September 2013 the GLA forecasts are expected to be approximately 60 (i.e. 2FE) higher than actual. Using their standard model forecasts and the same over forecast in September 2014, 2730 reception places plus Park Community School may be sufficient for September 2014, but contingency plans will be in place. TABLE 2- GLA 2013 STANDARD PROJECTION MODEL PUPIL FORECASTS BY SCHOOL PLACES PLANNING AREAS FOR STATUTORY SCHOOL YEARS
PLAN AREA 1 Hillside, Raynes Park and Village wards PLAN AREA 2 Cannon Hill, Lower Morden and West Barnes wards PLAN AREA 3 Abbey, Dundonald, Merton Park, Trinity and Wimbledon Park PLAN AREA 4 Ravensbury and St. Helier wards PLAN AREA 5 Colliers Wood, Cricket Green, Figge’s Marsh, Graveney and Lavender Fields PLAN AREA 6 Longthornton and Pollards Hill wards
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.