A. That Cabinet notes the financial reporting data relating to revenue budgetary control, showing a forecast underspend at year end of £954k (which is 0.58% of the gross Council Budget) after allowing for a £418k transfer to the Capital Programme B. That Cabinet notes the four schemes being re-profiled detailed in Appendix 5b and the Current Capital Programme as detailed in Appendix 5a. C. That Cabinet notes current progress to date on savings. D. That Cabinet notes the update to the use of reserves E. That Cabinet notes the update to Customer and Client Receipts F. That Cabinet notes the Cash Flow Statement G. That Cabinet notes the Key Strategic Risk Register as at September 2013 and approves the removal of the following four items: · KSR 51 – Supply Chain Failure - One of Merton's key delivery partners or sponsor goes in to administration – Risk Ranked as 2 · KSR 52 - Data quality of management information - Failure to provide accurate performance data – Risk Ranked as 2 · KSR 57 - Agency staff - Use of agency staff following changes to employment rights – Risk Ranked as 2 · KSR 59 - Business rates - Localism agenda - review of business rates Inc. discretionary reliefs – Risk Ranked as 2
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
A. That Cabinet discuss and comment on the financial reporting data relating to revenue budgetary control, showing a forecast underspend at year end of £954k (which is 0.58% of the gross Council Budget) after allowing for a £418k transfer to the Capital Programme and consider any relevant action they may wish to take in respect of variations B. That Cabinet discuss and comment on the four schemes being re-profiled detailed in Appendix 5b and the Current Capital Programme as detailed in Appendix 5a. C. That Cabinet discuss and comment on current progress to date on savings. D. That Cabinet discuss and comment on the update to the use of reserves E. That Cabinet discuss and comment on the update to Customer and Client Receipts F. That Cabinet discuss and comment on the Cash Flow Statement G. That Cabinet discuss and comment on the Key Strategic Risk Register as at September 2013 and Cabinet approve the removal of the following four items: KSR 51 – Supply Chain Failure - One of Merton's key delivery partners or sponsor goes in to administration – Risk Ranked as 2 KSR 52 - Data quality of management information - Failure to provide accurate performance data – Risk Ranked as 2 KSR 57 - Agency staff - Use of agency staff following changes to employment rights – Risk Ranked as 2 KSR 59 - Business rates - Localism agenda - review of business rates Inc. discretionary reliefs – Risk Ranked as 2
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 This is the regular financial monitoring report for 2013/14 presented to Cabinet in line with the financial reporting timetable. It is based on expenditure and income as at the half year to 30th September 2013.
-1- This financial monitoring report provides:-
• The latest budgetary control information on revenue expenditure and income, forecasting a year end underspend of £0.954m (£1.07.m underspend reported last month); • An update on the capital programme and detailed monitoring information; • An update on Corporate Items in the budget 2013/14; • Progress on the delivery of the 2013/14 revenue savings • An update on the use of reserves • An update on customer and client receipts • The key strategic risk register as at September 2013
2. 2013/14 FORECAST OUTTURN BASED UPON LATEST AVAILABLE DATA
2.1Executive summary - As at September, the forecast is expected to be a net £0.954m underspend compared to the current budget.
Summary Position as at 30th September 2013 Forecast Forecast Variance Current Full Year Variance at year Budget Forecast at year end 2013/14 (Sep.) end (Sep.) (Aug.) £000s £000s £000s £000s Department 3A.Corporate Services 11,942 10,883 (1,059) (670) 3B.Children, Schools and Families 50,880 51,853 972 602 3C.Community and Housing 63,568 63,711 142 (385) 3D.Public Health 0 (42) (42) (52) 3E.Environment & Regeneration 26,072 25,917 (155) 248 NET SERVICE EXPENDITURE 152,463 152,322 (140) (257)
3E.Corporate Items Impact of Capital on revenue budget 13,878 13,878 0 0 Central budgets (2,993) (3,807) (814) (814) Levies 914 914 0 0 TOTAL CORPORATE PROVISIONS 11,799 10,985 (814) (814) TOTAL GENERAL FUND 164,262 163,307 (954) (1,071) FUNDING Revenue Support Grant (47,221) (47,221) 0 0 Business Rates (32,020) (32,020) 0 0 Other Grants (8,356) (8,356) 0 0 Council Tax and Collection Fund (76,664) (76,664) 0 0 FUNDING (164,262) (164,261) 0 0 A detailed table is provided as Appendix 1.
Chart 1 below shows the forecast year end variance for departmental expenditure with a comparison against 2012/13.
-2- Service Expenditure - Forecast Year End 1,000 Variance 500
0 May
June
July
August
September
October
November
December
January
February
March Service -500 Expenditure 13/14 Service £'000
-1,000 Expenditure 12/13 -1,500
-2,000
-2,500
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.