RESOLVED A) That Cabinet noted the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £4.37 million, 2.69% of the net budget, a decrease of £0.9m from last month. B) That Cabinet approves the virements in Appendix 5B of the report: New Scheme: Jan Malinowsky Centre (JMC) Extension £200,000 Virement : Street Scene Enhancements (£235,000) Restoration of South Park Gardens £40,000 Figges Marsh Changing Rooms £50,000 Machinery for highways Grounds Maintenance £25,000 Dilapidations £65,000 Rebuild Unsafe Wall (with ‘charge’ placed on property) £55,000 Joseph Hood Primary Expansion (£136,480) Poplar Primary Expansion £136,480 C) That Cabinet approves the virement for the additional social work capacity required in Children, Schools and Families. The required virement of £127,900 from the coporate contingency. D) That Cabinet approves the virement of £216,000 over 2 years from OCPB reserves for temporary resources required for the Procurement Strategy to make procurement plans robust and deliver the council’s transformational needs and efficiency savings requirements. E) That Cabinet approves the virement of £200,000 over 2 years from OCPB reserves for the SLLP to provide the legal support for the above procurement activity. F) That Council is requested to add the conversion of ‘The Gables’, costing an estimated £577,300 to the Capital Programme, subject to reviewing the need for the legal charge/financial penalties and clarification of the financial benefit to the Authority.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Agenda Item 10 Cabinet Date: 10 November 2014 Subject: Financial Report 2014/15 – September 2014 Lead officer: Paul Dale
Lead member: Mark Allison
Recommendatiuons:
A. That Cabinet note the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £4.37 million, 2.69% of the net budget, a decrease of £0.9m from last month. B. That Cabinet approve the virements in Appendix 5b: New Scheme: Jan Malinowsky Centre (JMC) Extension £200,000 Virement Street Scene Enhancements (£235,000) Restoration of South Park Gardens £40,000 Figges Marsh Changing Rooms£50,000 Machinery for Highways Grounds Maint. £25,000 Dilapidations £65,000 Rebuild Unsafe Wall (with “charge” placed on property) £55,000 Joseph Hood Primary Expansion (£136,480) Poplar Primary Expansion £136,480
C. That Cabinet approve the virement for the additional social work capacity required in CSF. The required virement of £127,900 from the corporate contingency. D. That Cabinet approve the virement of £216,000 over 2 years from OCPB reserves for temporary resources required for the Procurement Strategy to make procurement plans robust and deliver the council’s transformational needs and efficiency savings requirements. E. That Cabinet approves the virement of £200,000 over 2 years from OCPB reserves for the SLLP to provide the legal support for the above procurement activity.
Page 77 PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 This is the regular financial monitoring report for 2014/15 presented to Cabinet(LSG) in line with the financial reporting timetable. It is based on expenditure and income as at 30th September 2014.
This financial monitoring report provides:-
x The latest budgetary control information on revenue expenditure and income, forecasting a
x year end overspend of £4.37m (last month £5.28m);
x An update on the capital programme and detailed monitoring information; An update on Corporate Items in the budget 2014/15;
2. 2014/15 FORECAST OUTTURN BASED UPON LATEST AVAILABLE DATA
2.1Executive summary - As at the half year to 30th September 2014 the forecast is expected to be a net £4.37m overspend compared to the current budget.
Summary Position as at 30st September 2014 Forecast Forecast Variance Current Full Year Variance at year Outurn Budget Forecast at year end variance 2014/15 (Sep) end (Sep) (Aug) 2013/14 £000s £000s £000s £000s £000s Department 3A.Corporate Services 13,286 12,799 (487) (492) (732) 3B.Children, Schools and Families 48,492 51,211 2,718 3,183 556 3C.Community and Housing 61,988 63,933 1,945 1,706 (1,122) 3D.Public Health 0 0 0 (0) 0 3E.Environment & Regeneration 24,212 25,545 1,333 1,875 (576) Overheads 0 0 0 0 55 NET SERVICE EXPENDITURE 147,978 153,488 5,509 6,272 (1,820)
3E.Corporate Items Impact of Capital on revenue budget 14,103 14,103 0 0 0 Central budgets (471) (1,614) (1,143) (991) 2,429 Levies 931 931 0 0 0 TOTAL CORPORATE PROVISIONS 14,563 13,420 (1,143) (991) 2,429
TOTAL GENERAL FUND 162,541 166,908 4,366 5,281 610 FUNDING Revenue Support Grant (39,738) (39,738) 0 0 (249) Business Rates (33,253) (33,253) 0 0 0 Other Grants (9,972) (10,053) (81) (81) (359) Council Tax and Collection Fund (79,578) (79,578) 0 0 0 FUNDING (162,543) (162,622) (81) (81) (610)
A detailed table is provided as Appendix 1.
It should be noted that C&H and CSF have netted down the forecast overspend by £915k of one-off Public Health money. This reduces the overall overspend from £5.3m to £4.37m reported.
Page 78 Chart 1 below shows the forecast year end variance for departmental expenditure with a comparison against both 2013/14 and 2012/13.
Chart 2 shows the forecast year end variance for corporate provisions with a comparison against both 2013/14 and 2012/13.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.