Period 9 Financial Monitoring Report

Noted Executive 1 paper

AI summaryMerton Cabinet notes a forecast revenue overspend of £0.785m at period 9, an improvement of £1.141m since period 8, and approves 18 revenue funding bids for civic pride and climate action.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedForecast revenue overspend noted; capital adjustments and 18 funding bids approved
Money£0.785m forecast overspendImprovement of £1.141m since period 8
What happens nextContinue recovery actionsFurther spending controls and savings delivery into year end
Who it affectsCouncil services and residentsDemand-led services, housing, and DSG-funded SEND provision

What was decided

Cabinet noted the period 9 financial reporting data showing a forecast General Fund overspend of £0.785m once corporate funding items are included, an improvement of £1.141m since period 8. Report P1, P30

Cabinet noted appendices 3 to 3c and approved the proposed adjustments to the capital programme in Appendix 3. Report P2, P47

Cabinet approved 18 revenue funding bids for civic pride, investing in neighbourhoods and climate action, as set out in Appendix 3b(i). Report P3

Why

The council is operating in a highly challenging financial climate with sensitive forecasts and demand-led pressures in adults' and children's social care and homelessness. Report P13, P14

Temporary accommodation and Children Services are the main drivers of the unfavourable variance, with mitigations including spend control, vacant post savings, and reviews of high-cost placements. Report P23, P24

The Dedicated Schools Grant high needs deficit continues to grow and is being managed under the Safety Valve programme and the statutory override extended to March 2028. Report P15, P16, P93, P119, P120

What happens next

Directorates will continue implementing mitigations, including a £2m in-year savings plan, agency cost reductions, and a comprehensive temporary accommodation recovery plan. Report P24

Capital programme adjustments approved in Appendix 3 will be reflected in the year-end capital monitoring and reported in future periods. Report P2, P47

The DSG deficit position and SEND reform developments, including the delayed White Paper, will inform the MTFS update. Report P17, P93

The money

  • £0.785m Forecast General Fund overspend including corporate funding items at period 9 Report P1, P30
  • £1.141m Improvement in forecast overspend since period 8 Report P1, P23
  • £5,924k Net service expenditure adverse variance at period 9 Report P28
  • £5.998m Housing and Sustainable Development adverse variance, mainly temporary accommodation Report P23, P190
  • £1.984m Children, Lifelong Learning and Families adverse variance Report P23, P27
  • £68.863m Forecast cumulative DSG deficit by end 2025/26 Report P16, P120
  • £53.556m Cumulative DSG deficit at end 2024/25 Report P16, P120

Options considered

  • Chosen: Note period 9 financial position and capital programme adjustments. Standard monitoring of in-year financial performance and capital programme changes Report P1, P2
  • Chosen: Approve 18 revenue funding bids for civic pride, neighbourhoods and climate action. To direct funding to civic pride, neighbourhood and climate action priorities Report P3

Implications

  • Financial: A final overall adverse variance on the General Fund would result in a call on council reserves. Report P11
  • Financial: The cumulative DSG deficit is forecast to exceed available reserves without a satisfactory resolution, posing a medium-term risk to reserves and cashflow. Report P16, P17
  • Risk: Temporary accommodation numbers continue to rise; Housing and Sustainable Development is the largest contributor to the overspend at £5.998m. Report P14, P23, P190
  • Risk: SEND reform is delayed; the Schools White Paper is now expected in early 2026, with a permanent solution to the DSG deficit still pending. Report P17, P93
  • Equalities: Adult Social Care is forecasting a £771k favourable variance, supported by the 2025/26 adult social care precept used to fund services for vulnerable adults. Report P127, P133
  • Climate: Approved revenue funding bids include investment in climate action alongside civic pride and neighbourhoods. Report P3
  • Staffing: Spend control measures include reductions in agency costs, savings from held vacant posts, and scrutiny of low-level spend across Directorates. Report P24

Who and where

  • Residents using temporary accommodation and homelessness services Report P14, P23
  • Children in care and families receiving CLLF services Report P78, P94
  • Adult Social Care service users and providers Report P133, P135
  • Children with SEND and their families (via the DSG High Needs Block) Report P15, P16, P116
  • Neighbourhoods and climate action initiatives (via the 18 approved revenue bids) Report P3

Timeline

  • 11 June 2025: Government confirmed approach to SEND reform as part of the Spending Review Report P17
  • Period 9 (December 2025): Financial monitoring position reported with £0.785m forecast overspend Report P1, P4
  • By end 2025/26: Cumulative DSG deficit forecast to reach £68.863m Report P16, P120
  • February 2026: Revised IDOX system implementation timeline for Public Protection Report P170
  • End March 2028: Statutory override separating DSG deficits from broader council finances is currently extended to Report P15
  • Early 2026: Schools White Paper on SEND reform is now expected, delayed from autumn 2025 Report P17, P93

Plain English for the jargon

  • DSG: Dedicated Schools Grant, the ring-fenced funding from the Department for Education covering schools, high needs, early years and central schools services blocks.
  • High Needs Safety Valve: A Department for Education programme for local authorities with significant DSG deficits, providing cash contributions alongside council contributions.
  • MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document.
  • NCIL: Neighbourhood Community Infrastructure Levy, developer contributions used for local infrastructure projects.
  • SEND: Special Educational Needs and Disabilities.
  • Period 9: The ninth financial monitoring period of 2025/26, covering the position as at December 2025.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

A That Cabinet note the financial reporting data for period 9 (December) relating to revenue budgetary control, showing a forecast overspend of £0.785m when corporate funding items are included, an improvement of £1.141m since period 8. B That Cabinet note the contents of the appendices 3 to 3c and approve the proposed adjustments to the capital programme in Appendix 3. C That Cabinet approve the 18 revenue funding bids for civic pride investing in neighbourhoods and climate action, detailed in Appendix 3b(i) A That Cabinet note the financial reporting data for period 9 (December) relating to revenue budgetary control, showing a forecast overspend of £0.785m when corporate funding items are included, an improvement of £1.141m since period 8. B That Cabinet note the contents of the appendices 3 to 3c and approve the proposed adjustments to the capital programme in Appendix 3. C That Cabinet approve the 18 revenue funding bids for civic pride investing in neighbourhoods and climate action, detailed in Appendix 3b( i )
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

A That Cabinet note the financial reporting data for period 9 (December) relating to revenue budgetary control, showing a forecast overspend of £0.785m when corporate funding items are included, an improvement of £1.141m since period 8.

B That Cabinet note the contents of the appendices 3 to 3c and approve the proposed adjustments to the capital programme in Appendix 3.

C That Cabinet approve the 18 revenue funding bids for civic pride investing in neighbourhoods and climate action, detailed in Appendix 3b(i):

Page 911 2. Executive summary 2.1 This is the period 9 monitoring report presented in line with the financial reporting timetable. The report provides:  A full year forecast projection.  An update on the capital programme and detailed monitoring information.

3. Relevance to strategic priorities, including Council Plan priorities Strategic priority Relevant Brief explanation of relevance

Building a sustainable x The report outlines the forecast financial position future of the Council for the year ending 31 March 2026. The financial health and sustainability of the authority underpin every area of the Council’s services and is therefore vital for delivering against the Council’s strategic priorities. Nurturing civic pride

Other service delivery priority

Organisational development

to strategic priorities, priorities

Page 912 Background, options and next steps

4. Introduction and background Chief Officers, together with budget managers and with support from finance officers, are responsible for keeping budgets under scrutiny and ensuring that expenditure within areas which are above budget is being actively and vigorously controlled. Any final overall adverse variance on the General Fund will result in a call on balances.

5. 2025/26 Forecast Revenue Outturn 6. 5/26 Forecast Revenue Outturn Executive Summary

Local authorities are operating in a highly challenging financial climate, with forecasts highly sensitive to interest rate and inflation fluctuations. Uncertainty caused by macroeconomic and geopolitical factors complicates forward funding, pay, and inflation projections.

Merton Council faces unprecedented pressures in demand-led services such as adults and children’s social care and homelessness. Temporary accommodation costs have surged sharply, contributing to the current forecast overspend, despite the Council having relatively low numbers in temporary accommodation compared to other London boroughs. Actions to mitigate these pressures have been implemented and will continue, as managing these challenges is critical for financial stability.

DSG A significant financial challenge is the Dedicated Schools Grant (DSG) High Needs budget, which has been in deficit since 2018/19. Merton joined the Department for Education’s High Needs Safety Valve programme in 2022 due to its significant deficits. The government introduced a statutory override to separate DSG deficits from broader council finances, extended until March 2028, which provides an accounting solution to the problem but does not solve the funding problem.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Period 9 Financial Monitoring ReportReport 2.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
SE
Sharon EvansCouncil Staff, in attendance
LA
Lewis Addlington-LeeCouncil Staff, expected
RG
Ross GarrodChair, present
ES
Eleanor StringerCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
AJ
Andrew JudgeCommittee Member, present
SK
Sally KennyCommittee Member, present
PM
Peter McCabeCommittee Member, present
UK
Usaama KaweesaCommittee Member, present
TO
Test OfficerCouncil Staff, expected
EM
Edith Macauley MBECommittee Member, present
SN
Stuart NeaversonCommittee Member, present

All 21 on the meeting page

On this subject at Merton

Search all
  1. Period 9 Financial Monitoring ReportThis decision
  2. Period 3 Financial Monitoring ReportNoted
  3. Period 8 Financial Monitoring ReportNoted
  4. Financial Monitoring Report 2025/26 - Period 5 (including The Merton Legacy Fund)Approved
  5. Period 3 Financial Monitoring ReportNoted
  6. Financial Monitoring Report Period 10Noted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies