RESOLVED That Cabinet 1. notes the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.285million, 0.83% of the net budget. 2. approves the following capital adjustments: 2015/16 2016/17 St Mary’s Expansion VAT Adjustment £137,210 Cricket Green Expansion (Grant) £459,740 Colliers Wood Library Re-Fit £200,000 Colliers Wood Library Relocation (£550,000) Rediscover Mitcham (S106) £507,280 Quietways Cycle Routes (TfL) £344,000 Canons Parks for People £124,000 £113,000 Street Lighting £400,000 Industrial Estates (£200,000) Town Centre Investments (£200,000) Total £1,312,490 £22,740 3. notes: i ) the re-profiling from 2015/16 to 2016/17 of £2,366k in Children, Schools and Families and £1,046k in Corporate Services. ii) that a report will be progressed to Council for the addition of Rediscover Mitcham to the capital programme and for the approval of the Education Section 106 funding already utilised to fund the capital programme. 4. approves the alternative revenue saving of £66,000 for Environment and Regeneration detailed in Appendix 6 to replace EN16 (previously agreed in 2013/14). 5. approves the release of up to £100k from the Council Board Issues reserve in relation to the Wimbledon Park Masterplan development.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
A. That Cabinet note the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.285million, 0.83% of the net budget.
B. That Cabinet Approve the following capital adjustments: 2015/16 2016/17 St Mary’s Expansion VAT Adjustment £137,210 Cricket Green Expansion (Grant) £459,740 Colliers Wood Library Re-Fit £200,000 Colliers Wood Library Relocation (£550,000) Rediscover Mitcham (S106) £507,280 Quietways Cycle Routes (TfL) £344,000 Canons Parks for People £124,000 £113,000 Street Lighting £400,000 Industrial Estates (£200,000) Town Centre Investments (£200,000) Total £1,312,490 £22,740 C. That Cabinet note: i) the re-profiling from 2015/16 to 2016/17 of £2,366k in Children, Schools and Families and £1,046k in Corporate Services. ii) That a report will be progressed to Council for the addition of Rediscover Mitcham to the capital programme and for the approval of the Education Section 106 funding already utilised to fund the capital programme.
-1- Page 1 D. That Cabinet approve the alternative revenue saving of £66,000 for Environment and Regeneration detailed in Appendix 6 to replace EN16 (previously agreed in 2013/14). E. That Cabinet approve the release of up to £100k from the Council Board Issues reserve in relation to the Wimbledon Park Masterplan development.
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 This is the first financial monitoring report for 2015/16 presented in line with the financial reporting timetable.
This financial monitoring report provides:-
x x The income and expenditure at period 2 and a full year forecast projection.
x An update on the capital programme and detailed monitoring information;
x An update on Corporate Items in the budget 2015/16;
x Progress on the delivery of the 2015/16 revenue savings An update on the delivery of 2014/15 savings
2. THE FINANCIAL REPORTING PROCESS
2.1The budget monitoring process will focus on budget pressures and potential overspending. The scale of the 2014/15 overspend needs to be addressed early in the current financial year to ensure measures are in place to address the scale of the potential overspend.
2.2Chief Officers, together with Service Financial Advisers and budget managers are responsible for keeping budgets under close scrutiny and ensuring that expenditure within budgets which are overspending is being actively and vigorously controlled and where budgets are under spent, these underspends are retained until year end. Any final overall overspend on the General Fund will result in a call on balances. The 2014/15 year end outturn highlights the need for close monitoring in this financial year.
-2- Page 2 2.3 2015/16 FORECAST OUTTURN BASED UPON LATEST AVAILABLE DATA
Executive summary – At period 2 to 31st May 2015 the year end forecast is a net £2.285m overspend compared to the current budget. Summary Position as at 31st May 2015
Forecast Current Full Year Variance Outurn Budget Forecast at year variance 2015/16 (May) end (May) 2014/15 £000s £000s £000s £000s Department 3A.Corporate Services 14,432 13,619 (813) (691) 3B.Children, Schools and Families 51,022 52,942 1,920 2,663 3C.Community and Housing 61,555 62,777 1,222 2,774 3D.Public Health 320 320 (0) (0) 3E.Environment & Regeneration 23,999 24,076 77 1,703 Overheads 0 0 0 0 NET SERVICE EXPENDITURE 151,328 153,734 2,406 6,448
3E.Corporate Items Impact of Capital on revenue budget 14,117 14,092 (25) 205 Central budgets (11,355) (12,451) (1,096) (2,817) Levies 926 926 0 0 TOTAL CORPORATE PROVISIONS 3,688 2,567 (1,121) (2,612)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies