That the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.8million, 0.3% of the gross budget be noted. 2. That the adjustments to the Capital Programme contained in Appendix 5b to the report be noted. 3. That the following adjustments to the Capital Programme be approved: S cheme 2017/18 Budget 2018/19 Budget Funding/Re-profiling Corporate Services Capita Housing (70,000) 70,000 Re-profiling Planning & Public Protection System 165,580 (165,580) Re-profiling Environment and Regeneration Rediscover Mitcham S106 224,650 0 S106 Funding Total 320,230 (95,580) 1. That the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.8million, 0.3% of the gross budget be noted. 2. That the adjustments to the Capital Programme contained in Appendix 5b to the report be noted. 3. That the following adjustments to the Capital Programme be approved: S cheme 2017/18 Budget 2018/19 Budget Funding/Re-profiling Corporate Services Capita Housing (70,000) 70,000 Re-profiling Planning & Public Protection System 165,580 (165,580) Re-profiling Environment and Regeneration Rediscover Mitcham S106 224,650 0 S106 Funding Total 320,230 (95,580)
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
A. That Cabinet note the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.8million, 0.3% of the gross budget. B. That Cabinet note the adjustments to the Capital Programme contained in Appendix 5b That Cabinet approve the following adjustments to the Capital Programme 2017/18 2018/19 Scheme Budget Budget Funding/Re-profiling Corporate Services Capita Housing (70,000) 70,000 Re-profiling Planning & Public protection System 165,580 (165,580) Re-profiling Environment & Regeneration Rediscover Mitcham Section 106 224,650 0 Section 106 Funding
Total 320,230 (95,580)
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 This is the financial monitoring report for quarter 1 and period 3, 30th June 2017 presented in line with the financial reporting timetable.
This financial monitoring report provides:-
• The income and expenditure at period 3 and a full year forecast projection. • An update on the capital programme and detailed monitoring information; • An update on Corporate Items in the budget 2017/18; • Progress on the delivery of the 2017/18 revenue savings
2. THE FINANCIAL REPORTING PROCESS
2.1The budget monitoring process in 2017/18 will continue to focus on adult social care and children’s social care as these areas overspent in 2016/17 and continue to have budget pressures.
2.2Chief Officers, together with budget managers and Service Financial Advisers are responsible for keeping budgets under close scrutiny and ensuring that expenditure within budgets which are overspending is being actively and vigorously controlled and where budgets are underspent, these underspends are retained until year end. Any final overall overspend on the General Fund will result in a call on balances as has been the case for the last two financial years, however this action is not sustainable longer term. Page 5 -1- 2.3 2017/18 FORECAST OUTTURN BASED UPON LATEST AVAILABLE DATA Executive summary – At period 3 to 30th June 2017 the year end forecast is a net £1.8m overspend compared to the current budget.
Summary Position as at 30th June 2017
Forecast Forecast Variance Variance Current Full Year at year at year Outturn Budget Forecast end end variance 2017/18 (June) (June) (May) 2016/17 £000s £000s £000s £000s £000s Department 3A.Corporate Services 26,426 26,297 (128) (131) (1,287) 3B.Children, Schools and Families 47,513 48,561 1,047 820 1,154 3C.Community and Housing 60,011 60,823 812 506 10,124 3D.Public Health (151) 50 50 121 16 3E.Environment & Regeneration 18,030 17,791 (239) (495) 1,011 Overheads 0 0 0 0 12 NET SERVICE EXPENDITURE 151,829 153,523 1,542 821 11,030
3E.Corporate Items Impact of Capital on revenue budget 13,415 13,457 42 42 193 Other Central budgets (19,701) (19,511) 190 643 (8,329) Levies 933 933 0 0 0 TOTAL CORPORATE PROVISIONS (5,353) (5,121) 232 685 (8,136) Less corporate overheads 405 TOTAL GENERAL FUND 146,071 148,401 1,774 1,506 2,894 FUNDING Revenue Support Grant (15,520) (15,520) 0 0 0 Business Rates (35,483) (35,483) 0 0 0 Other Grants (10,733) (10,733) 0 0 (537) Council Tax and Collection Fund (84,329) (84,329) 0 0 0 FUNDING (146,065) (146,065) 0 0 (537) 0 NET 5 2,336 1,774 1,506 2,357
The current level of GF balances is £12.778m and the minimum level reported to Council for this is £12.27m. This means that another reserve or further savings will need to be found to offset the remaining £1.27m overspend.
Page 6 -2- 3. DEPARTMENTAL SUMMARY OF CURRENT POSITION
Corporate Services Forecast Forecast variance variance 2017/18 Full year at year at year 2016/17 Current Forecast end end Outturn Budget June (June) (May) Variance
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.