Financial Monitoring Report 2017-18 - September 2017

Noted Executive 1 paper

Cabinet noted this item on Monday 13 November 2017. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

That financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.6million, 0.3% of the gross budget be noted. 2. That Cabinet and Council approve the following adjustments to the Capital Programme: Scheme 2017/18 Budget 2018/19 Budget Funding/Re-profiling £ £ Corporate Services Invest to Save schemes (1,710,000) 1,710,000 Re-profiling in accordance with projected spend Children, Schools & Families Sherwood Schools Capital maintenance 82,510 0 Essential H&S Works Cricket Green School Expansion 272,070 5,028,000 Vired from Unlocated SEN Unlocated SEN (272,070) (5,028,000) Vired to Cricket Green Harris Academy Wimbledon (544,530) 544,530 Re-profiling in accordance with projected spend Harris Academy Merton (70,120) 0 Capital Budget will be utilised under the Better Care Fund Environment & Regeneration Industrial Estates (452,750) 0 Budget relinquished as no plans to spend Morden Leisure Centre (1,255,830) 1,255,830 Slippage to 18/19 in line with current build programme. Total (3,950,720) 3,510,360 3. That in respect of capital expenditure incurred before 1 April 2008, Cabinet recommends to the Council that the Minimum Revenue Provision Policy be revised to read: “For capital expenditure incurred before 1 April 2008 or by Supported Capital Expenditure, the MRP policy will be the equal annual reduction of 2% of the outstanding debt at 1 April 2017 for the subsequent 50 years” The remainder of the MRP Policy Statement will remain as approved by Council on 1 March 2017. 1. That financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.6million, 0.3% of the gross budget be noted. 2. That Cabinet and Council approve the following adjustments to the Capital Programme: Scheme 2017/18 Budget 2018/19 Budget Funding/Re-profiling £ £ Corporate Services Invest to Save schemes (1,710,000) 1,710,000 Re-profiling in accordance with projected spend Children, Schools & Families Sherwood Schools Capital maintenance 82,510 0 Essential H&S Works Cricket Green School Expansion 272,070 5,028,000 Vired from Unlocated SEN Unlocated SEN (272,070) (5,028,000) Vired to Cricket Green Harris Academy Wimbledon (544,530) 544,530 Re-profiling in accordance with projected spend Harris Academy Merton (70,120) 0 Capital Budget will be utilised under the Better Care Fund Environment & Regeneration Industrial Estates (452,750) 0 Budget relinquished as no plans to spend Morden Leisure Centre (1,255,830) 1,255,830 Slippage to 18/19 in line with current build programme. Total (3,950,720) 3,510,360 3. That in respect of capital expenditure incurred before 1 April 2008, Cabinet recommends to the Council that the Minimum Revenue Provision Policy be revised to read: “For capital expenditure incurred before 1 April 2008 or by Supported Capital Expenditure, the MRP policy will be the equal annual reduction of 2% of the outstanding debt at 1 April 2017 for the subsequent 50 years” The remainder of the MRP Policy Statement will remain as approved by Council on 1 March 2017.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

A. That Cabinet note the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.6million, 0.3% of the gross budget. B. That Cabinet and Council approve the following adjustments to the Capital Programme

2017/18 2018/19 Scheme Funding/Re-profiling Budget Budget £ £ Corporate Services Invest to Save schemes (1,710,000) 1,710,000 Re-profiling in accordance with projected spend Children, Schools & Families Sherwood Schools Capital maintenance 82,510 0 Essential H&S Works Cricket Green School Expansion 272,070 5,028,000 Vired from Unlocated SEN Unlocated SEN (272,070) (5,028,000) Vired to Cricket Green Harris Academy Wimbledon (544,530) 544,530 Re-profiling in accordance with projected spend Harris Academy Merton (70,120) 0 Capital Budget will be utilised under the Better Care Fund Environment & Regeneration Industrial Estates (452,750) 0 Budget relinquished as no plans to spend Morden Leisure Centre (1,255,830) 1,255,830 Slippage to 18/19 in line with current build programme.

Total (3,950,720) 3,510,360

C. That in respect of capital expenditure incurred before 1 April 2008, Cabinet recommends to the Council that the Minimum Revenue Provision Policy be revised to read:

“For capital expenditure incurred before 1 April 2008 or by Supported Capital Expenditure, the MRP policy will be the equal annual reduction of 2% of the outstanding debt at 1 April 2017 for the subsequent 50 years”

The remainder of the MRP Policy Statement will remain as approved by Council on 1 March 2017.

Page 7 -1- 1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 This is the financial monitoring report for quarter 2, period 6, 30th September 2017 presented in line with the financial reporting timetable.

This financial monitoring report provides:-

• The income and expenditure at period 6 and a full year forecast projection. • An update on the capital programme and detailed monitoring information; • An update on Corporate Items in the budget 2017/18; • Progress on the delivery of the 2017/18 revenue savings

1.2This report also sets out Merton’s existing policy with regards to the calculation of Minimum Revenue Provision for Capital Expenditure incurred before 1 April 2008 or by Supported Capital expenditure which currently provides for MRP based on a 4% reducing balance methodology and proposes a change to a 2% straight-line basis.

The proposed change will mean that the calculation is done on a more prudent basis and will also result in a reduction in MRP set-aside until 2034.

2. THE FINANCIAL REPORTING PROCESS

2.1The budget monitoring process in 2017/18 will continue to focus on adult social care and children’s social care as these areas overspent in 2016/17 and continue to have budget pressures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Monitoring Report 2017-18: September 2017Report 966 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 22 attended
SA
Stephen AlambritisChair, present
MA
Mark AllisonCommittee Member, present
TB
Tobin ByersCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
ND
Nick DraperCommittee Member, present
RG
Ross GarrodCommittee Member, present
EM
Edith Macauley MBECommittee Member, present
KN
Katy NeepCommittee Member, present
MW
Martin WheltonCommittee Member, present
LF
Louise FlemingDemocracy Services, present
TO
Test OfficerCouncil Staff, expected
GC
Ged CurranOfficer, apologies

All 22 on the meeting page

On this subject at Merton

Search all
  1. Financial Monitoring Report 2017-18 - September 2017This decision
  2. Period 3 Financial Monitoring ReportNoted
  3. Period 9 Financial Monitoring ReportNoted
  4. Period 8 Financial Monitoring ReportNoted
  5. Financial Monitoring Report 2025/26 - Period 5 (including The Merton Legacy Fund)Approved
  6. Period 3 Financial Monitoring ReportNoted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies