CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Merton
Cabinet, Monday 12 July 2021 at 7.15pm

Parking Infrastructure and modernisation.

Approved Executive 2 papers

Cabinet approved this item on Monday 12 July 2021. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED that Cabinet: 1.1. Approved Option 1 as set out in section 5. To replace 78 existing high usage pay and display machines with new Payment Terminals commencing in October 2021. 1.2. Agreed to remove the remaining 334 low usage, cash (coin) only pay and display machines, and to remove a further 22 machines where an alternative upgraded payment terminal will be available and offer pay by RingGo or cash at local retail outlets. 1.3. Agreed to the introduction of the use of PayPoint at retail outlets throughout the Borough to allow for cash payments to be taken for pay to park at all on street parking locations. The current network of PayPoint retailers is set out in appendix 1C attached. 1.4. Approved the installation of:- 1.5. 28 new on street payment terminals with coin, card and contactless payment facilities , 33 new on street payment terminals with card (chip) and contactless payment facilities only as they are considered medium usage machines. 1.6. All 14 of the councils car parks will have at least one machine that accepts coins, contactless, and card (chip) payment facilities. These machines will also be able to produce a VAT receipt for customers on request. 3 car parks will have an additional machine with contactless and chip facilities due to high usage. 1.7. It is recommended that the cash facilities at new payment terminals in the Borough remain under review. The ability to remove the payment terminal cash boxes in Page 17 Agenda Item 72 the future will be determined by means of reviewing usage figures and customer payment patterns as demand for cash payments changes over the coming years. 1.8. Cabinet agreed to delegate authority to the Director of Environment and Regeneration, in consultation with the Cabinet Members for Regeneration, Housing and the Climate Emergency and Adult Social Care and Public Health, to finalise any operational matters in relation to the implementation of the proposals.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Payment Infrastructure Modernisation- Equalities Assessment (June 2021)

Equality Analysis

What are the proposals To modernise the existing parking infrastructure within the Borough in order to provide additional payment being assessed? options for residents and enable the digitisation of parking payments in line with other boroughs and the changing way people are choosing to make payments. Option 1 – To replace the existing dumb terminals with intelligent payment systems and continue the trend to reduce on Page 39

street payment infrastructure with a transition to online app (application) and mobile phone payments, allied to a network of PayPoint outlets for cash payments. In Option 1, some of the new payment terminals in high cash areas will be replaced with coin, chip and contactless, some will be replaced with chip and contactless only (in medium cash areas) and some will be removed altogether with RingGo (electronic payment) and PayPoint (cash) at local businesses, being the payment options available to motorists. Option 2 – To adopt a machine-less approach for the future where the existing on street payment terminals are removed and replaced with signage directing users to the mobile and on line apps for payment, allied to a network of PayPoint outlets for cash payments Cash alternative for both Options 1 & 2. To help facilitate the above options, all customers who may have no other means of paying for their parking other than by cash would be able to use a network of PayPoint outlets across the borough. There are 55 Pay Point retailers in Merton near to machine locations (which has the highest number of PayPoint providers in London). A map setting out the distribution and location of these PayPoint locations is attached as Appendix 1 to this report. PayPoint retailers provide an alternative cash payment infrastructure. When a customer enters a PayPoint location the customer would pay the shopkeeper in cash and their session would be uploaded to the RingGo solution. This is a payment option that is already in use across other London Boroughs, however with the migration to cashless options the uptake remains very low

Which Department/ Parking Services, Environment and Regeneration Division has the responsibility for this? Page 40

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parking Infrastructure and Modernisation Equalities AssessmentReport 241 KB DownloadRead as text
PDF
Parking Infrastructure and modernisation.Report 702 KB Download

At this meeting

Whole meeting

Who was there

4 of 9 attended
MA
Mark AllisonChair, present
TB
Tobin ByersCommittee Member, apologies
RL
Rebecca LanningCommittee Member, apologies
OP
Owen PritchardCommittee Member, present
MS
Marsie SkeeteCommittee Member, present
MW
Martin WheltonCommittee Member, present
TO
Test OfficerCouncil Staff, expected
AD
Amy DumitrescuDemocracy Services, in attendance
DH
Daniel HoldenCommittee Member, in attendance

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies