Financial Monitoring Report - Period 2 May 2021

Noted Executive 1 paper

Cabinet noted this item on Monday 12 July 2021. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

A. That Cabinet noted the financial reporting data for month 2, May 2021, relating to revenue budgetary control, showing a forecast net adverse variance at yearend on net service expenditure of £3.39m, reducing to £1.1m when corporate and funding items are included. B. That Cabinet approved a virement to transfer £46,820 budget from Corporate Services to C&H to reflect a change in structure for one post previously within the Client Financial Affairs team That Cabinet note the contents of Section 5 of the report and approve the adjustments to the Capital Programme in the Table below: Budget 2021-22 Budget 2022-23 Budget 2023-24 Budget 2024-25 Narrative £ £ £ Corporate Services Customer Contact (150,000) 150,000 0 0 Reprofiled in line with projected spend Payroll System 153,200 Drawdown from a Corporate Reserve Acquisitions Budget 200,000 0 0 (200,000) Property Purchase Community and Housing West Barnes Library Re-Fit (200,000) 200,000 Re-profiled Budget Children, Schools and Families Harris Morden - Morden Multi Sport Community Pitch 135,000 Virement to fund revised scheme Environment and Regeneration Morden Rec Hockey Pitch (135,000) Virement to fund revised scheme Pay and Display Machines- Emissions Based Charging 333,000 Virement to fund Emission Based Charging Scheme Car Park Upgrades (333,000) Virement to fund Emission Based Charging Scheme M orden Park Cycle Path 227,220 Additional TfL Funding Accesibility Programme 51,520 Additional TfL Funding Traffic Schemes 3,000 Additional TfL Funding Cycle Improve Residential Stre (9,210) S106 £20,550 Unallocated TFL (272,530) Virement from Unallocated TfL Budge Total 3,200 150,000 0 0 A. That Cabinet noted the financial reporting data for month 2, May 2021, relating to revenue budgetary control, showing a forecast net adverse variance at yearend on net service expenditure of £3.39m, reducing to £1.1m when corporate and funding items are included. B. That Cabinet approved a virement to transfer £46,820 budget from Corporate Services to C&H to reflect a change in structure for one post previously within the Client Financial Affairs team That Cabinet note the contents of Section 5 of the report and approve the adjustments to the Capital Programme in the Table below: Budget 2021-22 Budget 2022-23 Budget 2023-24 Budget 2024-25 Narrative £ £ £ Corporate Services Customer Contact (150,000) 150,000 0 0 Reprofiled in line with projected spend Payroll System 153,200 Drawdown from a Corporate Reserve Acquisitions Budget 200,000 0 0 (200,000) Property Purchase Community and Housing West Barnes Library Re-Fit (200,000) 200,000 Re-profiled Budget Children, Schools and Families Harris Morden - Morden Multi Sport Community Pitch 135,000 Virement to fund revised scheme Environment and Regeneration Morden Rec Hockey Pitch (135,000) Virement to fund revised scheme Pay and Display Machines- Emissions Based Charging 333,000 Virement to fund Emission Based Charging Scheme Car Park Upgrades (333,000) Virement to fund Emission Based Charging Scheme M orden Park Cycle Path 227,220 Additional TfL Funding Accesibility Programme 51,520 Additional TfL Funding Traffic Schemes 3,000 Additional TfL Funding Cycle Improve Residential Stre (9,210) S106 £20,550 Unallocated TFL (272,530) Virement from Unallocated TfL Budge Total 3,200 150,000 0 0
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

A. That Cabinet note the financial reporting data for month 2, May 2021, relating to revenue budgetary control, showing a forecast net adverse variance at yearend on net service expenditure of £3.39m, reducing to £1.1m when corporate and funding items are included. B. That Cabinet approve a virement to transfer £46,820 budget from Corporate Services to C&H to reflect a change in structure for one post previously within the Client Financial Affairs team That Cabinet note the contents of Section 5 of the report and approve the adjustments to the Capital Programme in the Table below: Budget Budget Budget Budget Narrative 2021-22 2022-23 2023-24 2024-25

£ £ £

Corporate Services

Customer Contact (150,000) 150,000 0 0 Reprofiled in line with projected spend

Payroll System 153,200 Drawdown from a Corporate Reserve

Acquisitions Budget 200,000 0 0 (200,000) Property Purchase

Community and Housing

West Barnes Library Re-Fit (200,000) 200,000 Re-profiled Budget

Children, Schools and Families

Harris Morden - Morden Multi Sport Community Pitch 135,000 Virement to fund revised scheme

Environment and Regeneration

Morden Rec Hockey Pitch (135,000) Virement to fund revised scheme

Pay and Display Machines- Emissions Based Charging 333,000 Virement to fund Emission Based Charging Scheme

Car Park Upgrades (333,000) Virement to fund Emission Based Charging Scheme

Morden Park Cycle Path 227,220 Additional TfL Funding

Accesibility Programme 51,520 Additional TfL Funding

Traffic Schemes 3,000 Additional TfL Funding

Cycle Improve Residential Stre (9,210) S106 £20,550

Unallocated TFL (272,530) Virement from Unallocated TfL Budget

Total 3,200 150,000 0 0

1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 This is the period 2 monitoring report for 2021/22 presented in line with the financial reporting timetable. This financial monitoring report provides -  A full year forecast projection as at period 2.  An update on the financial impact of Covid-19  An update on the capital programme and detailed monitoring information;  An update on Corporate Items in the budget 2021/22;  Progress on the delivery of the 2021/22 revenue savings,

Page 167 2. THE FINANCIAL REPORTING PROCESS

2.1The budget monitoring process for 2021/22 continues to focus on the ongoing financial impact of Covid-19. The Council’s services remain under pressure due to the need to support businesses and residents, particularly vulnerable groups in need of social care and there has been a major reduction in the Council’s income which is expected to continue for some time. The detrimental impact of Covid-19 is being monitored closely as the situation evolves with lifting of restrictions.

2.2There are also significant pressures on the Dedicated Schools Grant (DSG) which are being monitored. The cumulative deficit at the end of 2020/21 was £24.981m and the deficit is forecast to continue to increase in 2021/22, the cumulative deficit is now estimated to be £38.432m by the end of this financial year.

2.3Chief Officers, together with budget managers and Service Financial Advisers are responsible for keeping budgets under close scrutiny and ensuring that expenditure within areas which are above budget is being actively and vigorously controlled and where budgets have favourable variances, these are retained until year end. Any final overall adverse variance on the General Fund will result in a call on balances.

3. 2021/22 FORECAST OUTTURN BASED UPON LATEST AVAILABLE DATA

Executive summary – At period 2 to 31st May 2021, the yearend forecast is a net adverse variance of £0.657m when all incremental Covid costs are included, after applying known government grant funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Monitoring Report: Period 2 May 2021Report 808 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 9 attended
MA
Mark AllisonChair, present
TB
Tobin ByersCommittee Member, apologies
RL
Rebecca LanningCommittee Member, apologies
OP
Owen PritchardCommittee Member, present
MS
Marsie SkeeteCommittee Member, present
MW
Martin WheltonCommittee Member, present
TO
Test OfficerCouncil Staff, expected
AD
Amy DumitrescuDemocracy Services, in attendance
DH
Daniel HoldenCommittee Member, in attendance

On this subject at Merton

Search all
  1. Financial Monitoring Report - Period 2 May 2021This decision
  2. Period 3 Financial Monitoring ReportNoted
  3. Period 9 Financial Monitoring ReportNoted
  4. Period 8 Financial Monitoring ReportNoted
  5. Financial Monitoring Report 2025/26 - Period 5 (including The Merton Legacy Fund)Approved
  6. Period 3 Financial Monitoring ReportNoted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies