That Cabinet considered and agreed the draft Capital Programme 2022-2031 and referred it to the Overview and Scrutiny panels and Commission in January 2022 for consideration and comment. 2. That the Cabinet noted the details set out in the Government’s Autumn Budget 2021 and Spending Review 2021. 1. That Cabinet considered and agreed the draft Capital Programme 2022-2031 and referred it to the Overview and Scrutiny panels and Commission in January 2022 for consideration and comment. 2. That the Cabinet noted the details set out in the Government’s Autumn Budget 2021 and Spending Review 2021.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
1. That Cabinet considers and agrees the draft Capital Programme 2022-2031 and refers it to the Overview and Scrutiny panels and Commission in January 2022 for consideration and comment.
2 That the Cabinet notes the details set out in the Government’s Autumn Budget 22021 and Spending Review 2021.
1. Purpose of report and executive summary
1.1This report provides an update on the Council’s progress towards developing a Business Plan for 2022-26. In particular, it sets out the latest financial information relating to the MTFS 2022-26 and its impact on the requirement to set a balanced budget and Council Tax for 2022/23.
1.2There is an update on the current information available relating to local government finance and relevant financial and economic factors which will have an important bearing on the Council’s approach to balancing the budget. This includes a summary of the relevant details announced in the Autumn Budget 2021 and Spending Review 2021.
1.4There is an update on the potential impact in 2022/23 and possibly beyond, of the coronavirus pandemic which first impacted at the end of the 2019/20 financial year and is still impacting throughout the current financial year.
Page 5 1.5 There is an update on the potential impact in 2022/23 and possibly beyond, of other factors such as inflation, that may affect Council services in the MTFS period.
1.6Finally, there is an update on the Council’s draft capital programme 2022-31 and the ongoing revenue impact of that programme.
Details
Background
2.1The last report to Cabinet on 11 October 2021 set out the set out the approach towards setting a balanced budget for 2022-2026 and a draft timetable for the business planning process for 2022/23. It also proposed initial departmental targets to be met from savings and income over the four year period of the MTFS.
2.2The report emphasised the high degree of economic and financial uncertainty which surrounds local government finance at the present time and presented an updated MTFS 2022-26 based on the latest information available.
2.3The report to Cabinet in October presented an updated MTFS which rolled forward the previous year’s by one year, re-priced for the latest inflation forecasts, and included some assumptions about potential expenditure pressures, capital financing costs arising from a draft capital programme including some new bids, and potential use of reserves.. On this basis the MTFS gap was as follows:-
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.