RESOLVED : 1. That Cabinet noted the approach to rolling forward the MTFS for 2024-28 2 That Cabinet noted the initial reallocation of budgets to reflect the new Council structure into six directorates 3 That Cabinet agreed the approach to strengthening transparency in financial management, and the revised process for the 2024/25 budget round.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
1. That Cabinet notes the approach to rolling forward the MTFS for 2024-28 2 That Cabinet note the initial reallocation of budgets to reflect the new Council structure into six directorates 3 That Cabinet agrees the approach to strengthening transparency in financial management, and the revised process for the 2024/25 budget round.
1. Purpose of report and executive summary 1.1 This report presents an initial review of the Medium Term Financial Strategy and updates it for development as part of the business planning process for 2024/25.
1.2The report sets out proposed revisions to the budget process to strengthen transparency in financial management as an approach towards setting a balanced budget for 2024-2028.
1.3A key element of the report is to set out the budget in the new management structure featuring the six new directorates compared to the previous four departments which were included in the budget papers agreed by Council in March 2023. The realignment is an initial step and it is acknowledged that further movement of budget may be needed as the financial year proceeds.
1.4Given the current high level of uncertainty over a range of factors that have the potential to impact significantly on the MTFS there is a sensitivity analysis of a number of issues including the potential impact across the MTFS period of current issues that impact on local government such as the continuing current high level of inflation and also specific issues such as addressing the DSG deficit.
Page 361 Details
2. Changes to the Budget Process and Timetabling
2.1A lot was achieved in a short time to complete the MTFS work for 2023/24 onwards despite a late start in the process whilst also ensuring a wider engagement and transparency in the mechanics of the budget. We are now in a position to take a more measured and systematic approach to the MTFS process for 2024/25 onwards.
2.2A key objective during this financial year will be to strengthen our Financial Management Framework, the key components of which are:
• Financial Governance and Leadership – top management are financially literate and understand the Council’s financial environment. • Financial Planning – ensuring strong links between the strategic plan and the Financial Plan. • Financial decision making – reviewing where budgets are aligned to achieve strategic and corporate plans. • Financial monitoring and forecasting – strengthening financial monitoring and budget ownership. • Financial Reporting – that budget managers receive accurate, timely and intelligible financial information and are properly supported by Finance colleagues.
3. Medium Term Financial Strategy 2024-28
Background
Council on 1 March 2023 agreed the Budget 2023/24 and MTFS 2023-27. It was a significant achievement to set a balanced budget for both 2023/24 and 2024/25 but there is a gap remaining in future years which needs to be addressed, and in 2027/28 the gap increases significantly mainly due to the impact of the capital programme as shown in the following table:-
3.2The initial phase of the business planning process is to re-price the MTFS and roll it forward for an additional year. Development of the MTFS in recent budget processes allowed for various scenarios on a range of key variables to be modelled and it is intended to do the same this year and where feasible, to improve the approach to modelling.
Page 362 Regular updates will be provided throughout the year as part of Business Planning reports for the MTFS period 2024-28 and the estimated impact of inflation, the capital programme and other significant budget issues incorporated into the forecast.
Budget Restructure
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.