AI summaryMerton Cabinet agreed to run a procurement for a new three-year Microsoft Enterprise Agreement through the Crown Commercial Services TePAS2 framework, with the new contract estimated at £2,940,000 excluding VAT and starting 1 April 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedUse CCS TePAS2 framework, award to follow
Money£2,940,000 ex VAT over 3 yearsEstimated new contract value, £3,528,000 inc VAT
What happens nextContract starts 1 April 2026Subject to CCS Aggregation result
Who it affectsCouncil Microsoft product usersServers, desktops and applications across the council
What was decided
Cabinet agreed to procure the Microsoft Enterprise Agreement through the Crown Commercial Services TePAS2 framework. Report P1
Cabinet also agreed in principle to award the contract to the winning supplier once the CCS Aggregation has run. Report P1
Merton is not bound to accept the winning supplier and can clarify service and quality expectations first. Report 6.2
Why
Microsoft have announced a 12-14% price uplift on products from May 2026, and the current three-year Large Account Reseller contract is in its final year. Report 2.3, 2.5, 2.7
Re-tendering now via CCS Aggregation would let Merton lock in current prices and avoid an estimated cost increase of £117,594.50 at the next renewal. Report 2.7, 2.8, 2.9
The CCS TePAS2 framework is recommended as a compliant route to market and was successfully used by Merton in 2022. Report 4.7, 7.1, 8.4
What happens next
The CCS Aggregation was scheduled to reveal the winning bidder and final cost on 9 February 2026, with Cabinet approval sought on 16 February 2026. Report P89, 8.5
The new contract is due to commence on 1 April 2026, subject to Merton's agreement to enter the term with the winning supplier. Report P89, 6.2
CCS will also carry out a free benchmark review of Merton's licences, flagging deprecated items and possible alternative products ahead of the March 2026 renewal. Report 8.6
The money
£2,432,001.06 Total 3-year cost of existing contract (ex VAT) Report P3, P4
£2,918,401.272 Actual costs of existing contract (inc VAT) Report P3
£2,940,000 Estimated total value of new contract over 3 years (excl VAT) Report P5, 6.4
£3,528,000 Estimated total value of new contract over 3 years (inc VAT) Report P5, 6.4
£979,954.20 Estimated current EA cost for 2026-27 Report 2.7
£117,594.50 Potential cost increase from a 12% Microsoft price rise Report 2.7, 2.8
£1,000,970 Current budget on cost code 101570-3521 Report P93
Options considered
Rejected: Do nothing: do not renew Microsoft licences. Core systems and applications would stop working within 6 months and risk financial penalties for being un-licensed; cost would rise 12-16% if re-procured later Report P41, P45, P46, P48
Rejected: Extend the existing LAR contract by 12 months. Microsoft's 12% price rise would still apply, adding an estimated £117,594.50 to the next renewal Report P50, P54, P55, P57
Chosen: Retender the EA via the CCS TePAS2 framework using the CCS Aggregation. Most cost-effective option; locks in current prices for 3 years with estimated year 1 cost avoidance of £117,594.50; CCS validates the winning supplier Report P58, P60, P62, P63, 6.1, 7.3
Rejected: Move to an alternative operating system and desktop applications. Would still need some Microsoft licences, would create a hybrid platform with technical and training challenges, would take over 18 months and has unquantified cost Report P65, P67, P68, P69
Implications
Financial: Re-tendering now is forecast to avoid a 12% Microsoft price rise and give licence and price stability for the next 3 years; current budget of £1,000,970 is expected to cover annual costs. Report 2.7, 2.9, 2.10, P62, P93
Legal: Use of the TePAS2 framework is permitted under Contract Standing Orders (CSO 12) and governed by the Public Contracts Regulations 2015; the call-off must follow the framework's buyer guide and be published on Contracts Finder. Report P93
Risk: Merton will be locked in with a specific Large Account Reseller and tied to Microsoft product changes for the 3-year term. Report P61
Equalities: Officers judged the decision to have remote or low relevance to the Equality Act; a Corporate Equality Analysis form is on file. Report P93, P94
Climate: The decision is judged to have remote or low impact on the Climate Strategy & Action Plan; the TePAS2 framework encourages carbon reduction plans and sustainable solutions. Report P95
Other: Joining the aggregation with 13 other local authorities increases economies of scale and combines requirements to reduce costs over the 3-year term. Report 7.4, P96
Who and where
Merton Council's digital infrastructure, servers, desktops and office applications Report 4.1, 2.1
The council's IT Service Delivery team Report P2, P98
13 other local authorities taking part in the same CCS Aggregation Report 7.4
The incumbent Large Account Reseller (whose final year of the current contract is ending) Report 2.3, 2.4
Timeline
9 February 2026: CCS reveal of winning bidder and final cost from the aggregation Report P89
16 February 2026: Cabinet decision to approve procurement route and in principle award Report P89
1 April 2026: Contract commencement date for the new Microsoft Enterprise Agreement Report P89
May 2026: Microsoft price increase of around 12-14% takes effect for renewing customers Report 2.5
Plain English for the jargon
LAR (Large Account Reseller): An authorised reseller through which the council must buy Microsoft licences, as Microsoft does not sell direct.
EA (Enterprise Agreement): A three-year subscription licence agreement with Microsoft for using its products.
CCS (Crown Commercial Services): A government body that runs framework agreements and aggregation procurements for the public sector.
TePAS2 (Technology Products & Associated Services 2): A CCS framework agreement recommended for re-tendering this contract.
SPA24: The Microsoft pricing agreement that replaced DTA21 in November 2024, governing current licence discounts.
Aggregation: A CCS-run mini-competition combining the licence requirements of multiple public sector bodies to secure better reseller margins.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
That Cabinet is asked to: A. Agree the procurement process for the using Crown Commercial Services (CCS) TePAS2 framework agreement. B. Agree the award of the contract to the winning supplier following the outcome of the CCS Aggregation. That Cabinet is asked to: A. Agree the procurement process for the using Crown Commercial Services (CCS) TePAS2 framework agreement. B. Agree the award of the contract to the winning supplier following the outcome of the CCS Aggregation.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
That Cabinet is asked to: A. Agree the procurement process for the Microsoft Enterprise Agreement using Crown Commercial Services (CCS) TePAS2 framework agreement. B. Agree the award of the contract to the winning supplier following the outcome of the CCS Aggregation.
Page 219 Report summary and relevance to strategic priorities Procurement Details Summary – Direct Award Contract Manager / Project Manager Richard Warren (Name and Title) Head of IT Service Delivery Name and description of Contract Microsoft Enterprise Agreement
Is the Contract for No Goods/Works/Services that are a To allow the Council to be licenced to use Statutory Requirement? the latest Microsoft products. This will be organised via an Enterprise Agreement (EA) using a Large Account Reseller (LAR). Total Value of Existing Contract £2,432,001.06 ex VAT Actual Costs: £2,918,401.272 inc VAT
Total 3 Year cost: £2,432,001.06 (excluding VAT) Rate of applicable VAT VAT @ 20%
See gov.uk guidance here Estimated Total Value of New Contract £2,940,000 (excl VAT) over 3 years: £3,528,000 (inc VAT) VAT @ 20%
Final Cost of New Contract over 3 Expected Tuesday 10 February 2026: years (Following results of CCS £ ex VAT Aggregation procedure): £ inc VAT VAT @ 20% Does the current provider pay staff Yes working on the Merton contract London Living Wage (LLW) or above? If this is a new contract, will the new provider pay LLW as per Merton’s policy requirements? If no, please explain why
Page 220 2. Executive Summary
2.1The Council uses Microsoft products to provide its digital infrastructure technology and supporting services. The licences that we purchase from Microsoft are provisioned via a subscription licence agreement that is renewed annually.
2.2Microsoft so not sell these licences directly and require us to engage with a Large Area Reseller (LAR) in order to buy these products.
2.3Our incumbent LAR has provided our MS licence management service for three years and we are now in our final year of the three-year contract.
2.4We are able to extend this three-year contract by another year which would enable us to continue to renew our EA with Microsoft.
2.5However, Microsoft have recently announced a price increase which would affect a number of products that we currently purchase. This price increase will take effect from May 2026. This Microsoft pricing consistency update will see a price uplift of approximately 12-14% for customers renewing from May 2026 onward.
2.6Although the CCS are in discussions with Microsoft and the Crown Representative to minimise the impact of this uplift as much as possible, there is likely to be an agreement by Microsoft to phase these increases over a period of time. However, at the time of this report writing, this arrangement has not been confirmed.
2.7The current EA cost for 2026-27 is estimated to be £979,954.20. If we do not retender the EA now, in order to lock in the current costs, we could expect an increase of up to £117,594.50 at our next renewal in March (based on a 12% increase)
2.8There is an urgency for us to retender now (as opposed to carrying out a contract extension with the current LAR) and commence a new 3-year term agreement with a new LAR at our next renewal in March 2026 to avoid the cost increase of £117,594.50.
2.9Retendering now will allow us to secure the current licence price levels for the next 3 years avoiding the price increases which will commence from May 2026.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.