That Cabinet: (a) endorse the project plan and accept receipt of grant funding of £583,500 from the Department for Levelling Up Housing and Communities (DLUHC), which will be drawn down in arrears; and (b) approve an increase in the Capital Programme of £583,500 in 2023/24 fully funded by DLUHC grant.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1In preparation for the East Midlands Combined Authority the Department for Levelling Up, Housing and Communities (DLUHC), has allocated a total of £18m of capital funding to Derbyshire County Council as the Lead Funder on behalf of the four Constituent Councils who will form part of the EMCAA, if approved. Each local authority has been allocated £583,500. 1.2 On 13 September 2023, the Council received confirmation that £583,000 had been allocated and the Mobilization Grant Offer letter has been signed and returned by our S151 Officer on 3rd October 2023.
1.3The project will deliver domestic energy efficiency and low carbon retrofit activities within Newark and Sherwood District Council and report through The Midlands Net Zero Hub (MNZH) funded by the Department for Energy Security as part of the Government’s clean growth strategy, hosted by Nottingham City Council.
1.4The Council are currently working with MNZH as part of the Social Housing Decarbonisation Fund (SHDF) Wave 2.1 project to deliver carbon neutral heating, solar and air source to 102 council owned homes. The objectives of this scheme being:
85 Whole House Retrofit approach scaled with all compliant required SAP measures installed (Target of 5 homes per Local Authority) 600 PAS2035 compliant measures installed (Target of 36 per Local Authority) Improved health and wellbeing for home occupiers through a pre and post survey Reduced consumption and lower carbon footprint. Reduced number of households below an EPC C Average Standard Assessment Procedure (SAP) improvement
1.5As NSDC is already in delivery mode, working on SHDF, this project is seen as an extension of this work, with all works meeting PAS 2035 standards and certificated by Trustmark.
1.6All measures are expected to be signed up to receive measures in period October – December 2023 and be completed by June 2024.
1.7Grant allocation will be based on a monthly claim and completion of the monthly monitoring form and payment made within 30 working days of evidence of the payment date agreed.
2.0Proposal
2.1The proposal is outlined in Appendix 1 and this meets the grant funding requirements and will deliver 51 decarbonisation or energy saving measures in a further 38 social housing homes.
2.2These properties have been selected because either/or:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.