Resolved
That Cabinet: a) notes the progress and expected completion of the current HRA Development Programme; b) allocates £234,747.64 from Section 106 contributions (as detailed in section 2.16 of the report) to development sites at South Crescent, Clipstone; Firview, Ollerton; and Gaitskell Crescent, Edwinstowe as part of Phase 5 of the HRA Development Programme therefore reducing the required borrowing by an equivalent amount; c) supports the creation of £10.7m budget for the development of a discreet programme of HRA Development up to 50 units within the HRA Capital Programme in 2024/25 financed by the surplus identified at paragraph 2.19 of the report of £2.445m and with the remaining £8.255m financed initially from borrowing whilst other funding is sourced; and d) commits the total of £1.292m from the Section 106 agreements listed at section 2.21 of the report to the new development programm e within the obligations of the S106 agreements.