That Cabinet: (a) approves an additional transfer of £161,800 funded from the Change Management Reserve, giving a total Capital budget of £740,000 to carry out the essential works to the dry side facility as set out in this report; (b) note that whilst every effort will be made to phase the works to keep the Leisure Centre operational at all times , there is a possibility that the Leisure Centre may have to close for a period of time in order for the works to be carried out safely, effectively and efficiently; and (c) note that in the event of closure, Active4Today will endeavour to accommodate customers at the Newark and Dukeries facilities, and that the Leisure Centre members affected will have their direct debits reduced to a nil payment where appropriate.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1The management of the Southwell Leisure Centre was transferred to Newark & Sherwood District Council (NSDC) in 2021, with the operational responsibilities being carried out by Active4Today. At the end of 2022 and the beginning of this year, fire safety inspections and subsequent surveys identified works that were required for the building to be fully compliant. Some of these works that related to the first floor were carried out in January of this year, after a short closure of the first-floor fitness suite and staff offices. The surveys, however, identified further fire safety and general repair works that needed to be undertaken. A more recent survey of the main pool and the learner pool carried out by a swimming pool specialist has reported significant defects in the infrastructure of the main pool.
1.2Corporate Property have approached Lindum, based in Lincoln, to undertake a full feasibility of a programme of works required to the dry side facility prior to a potential instruction through the SCAPE framework. SCAPE frameworks are designed to deliver value for money on construction projects that are delivered on time and on budget. Lindum have produced an indicative programme for the works and cost estimates, however if Lindum were to proceed on the basis of a direct award under the SCAPE framework, they would firm up costs by seeking three quotes on all items where necessary.
2.0Works Overview
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.