Resolved
AGREED that any decision on repairing the bridge be deferred to a future meeting of the Cabinet to enable officers to establish the responsibilities of the County Council in terms of adoption and maintenance.
Cabinet agreed this item on Tuesday 26 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED that any decision on repairing the bridge be deferred to a future meeting of the Cabinet to enable officers to establish the responsibilities of the County Council in terms of adoption and maintenance.
1.1A report was presented to members in February 2023 detailing the proposed works with a series of options which could be selected in order to upkeep and maintain Jubilee Bridge. These options included estimated costs forecasted by an external Quantity Surveyor (QS) appointed by N&SDC.
1.2Since this report was received by Members in February 2023, Corporate Property have undertaken a procurement excise for the options of repair outlined in the report. The purpose of this update report is to give Members an update of the costs received through the tender excise. With a request for a change in the recommended option from the Cabinet on the grounds of value for money. 2.0 Proposal/Details of Options Considered
2.1A procurement exercise was undertaken by Corporate Property in the summer of 2023. This gave contractors an opportunity to price for all required repair options (as detailed in the table below).
2.2The outcome of this procurement exercise was that the tender returns were vastly beyond those forecasted by the quantity surveyor (QS) appointed by N&SDC. The cheapest contractor for all three repair options was Hankinson Whittle. They also scored highly on the quality assessment of the tender. A summary of the Hankinson Whittle submitted tender costs for each repair option is outlined in the table below alongside the costs estimated by the consultant quantity surveyor (QS) for each option. An explanation of the difference between the QS estimates and the tendered price return has been received. The consultant quantity surveyor stated that “The cost plan was prepared by a QS as a ‘current’ cost at the time the specification was initially compiled and when the tender returns were received, market costs had increased due to a mix of design development and construction market factors in 2023.’’
Option Predicted life Estimated cost by Lowest cost submitted expectancy Consultancy and received by Quantity Surveyor tendering contractor Option 1 – Replace existing 20 – 25 years £314,296.67 + Vat £321,624.60 + Vat softwood deck boards with hardwood timber boards Option 2 – Replace existing with 30 – 35 years £323,899.67 + Vat £487,832.40 + Vat a mild steel deck which is coated with a shell grip type anti-slip coating / finish Option 3 – Replace existing with 30 – 35 years £333,499.67 + Vat £536,960.60 + Vat steel trays which are infilled with Tarmacadam to match the existing bridge
2.3The preferred option recommended to Members in February 2023 was to refurbish the Jubilee Bridge as per Option 3, i.e. Replacing the existing softwood timber approach ramps with steel trays which are infilled with Tarmacadam to match the existing bridge. This was because of the predicted lifespan and durability of the product compared to cost, was justifiable at the time of reporting.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on Jubilee Bridge Maintenance Costs (Key Decision)Decisions | 470 KB | DownloadRead as text |
Follow Cabinet at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... | Noted | Open |
| 15 Sep 2026 | Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... | Decided | Open |
| 15 Sep 2026 | Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... | Decided | Open |
| 15 Sep 2026 | Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. | Noted | Open |
| 15 Sep 2026 | Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.