Sherwood Levelling Up 3 Update - Ollerton and Clipstone (Key Decision)

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 26 March 2024. Below is the council's own wording, with the papers it was decided on.

Item119

Resolved

AGREED that Cabinet: a) note and welcome the progress on the LUF 3 projects: Ollerton b) to add the requisite budget to the Council’s Capital Programme as detailed in the exempt Appendix to cover the full costs of the acquisition and ongoing holding of the former Lloyds Bank Building until such time as the building is absorbed into the delivery of the Ollerton Town Centre LUF 3 scheme; c) to require presentation to a future Cabinet of a final Business Case for the Ollerton Town Centre Regeneration, including updates on funding, risk, any Council commitments (capital and revenue), programme, delivery route (procurement) and a request to include the project within the Council’s capital programme; d) delegate to the Portfolio Holders for Strategy, Performance & Finance and Sustainable Economic Growth in consultation with the Director – Resources and Director - Planning & Growth, authority to negotiate and enter legal options to purchase in accordance with the requirements of the Council’s Acquisitions and Disposals Policy the land holdings required for the Ollerton Town Centre scheme (from Ollerton & Boughton Town Council and Johal Ltd) for the Maximum Offers detailed at Exempt Appendix A, subject to planning permission and a decision from Cabinet to implement the scheme. e) delegate to the Director - Resources, in consultation with the Director - Planning & Growth, Business Manager - Corporate Property and Portfolio Holders for Strategy, Performance & Finance and Sustainable Economic Growth , authorisation to negotiate and seek formal commitments from Nottinghamshire County Council to secure a financial commitment for the Minimum amount in Exempt Appendix A and Tesco to secure ongoing commitment to the Public Transport Hub and car parking provision for patrons of this development and the wider Town Centre. Clipstone f) to require presentation to a future Cabinet of a final Business Case for the Clipstone Mansfield Road Regeneration project (Phases 2 and 3), including updates on funding, risk, any Council commitments (capital and revenue), programme, delivery route (procurement) and a request to include the project within the Council’s capital programme; g) delegate to the Portfolio Holders for Strategy, Performance & Finance and Sustainable Economic Growth in consultation with the Director – Resources and Director - Planning & Growth authorisation to negotiate and secure ongoing commitments from the Clipstone Miners Welfare Trust to ensure the District Council will have an ongoing role in the governance and management of any new Sports Facility associated with Phase 2 of the Mansfield Road Clipstone regeneration project; h) delegate to the Portfolio Holders for Strategy, Performance & Finance and Sustainable Economic Growth in consultation with the Director – Resources and Director - Planning & Growth authorisation to negotiate and seek formal commitments from Welbeck Estates for any land purchase or land swap to facilitate Phase 3 of the Mansfield Road Clipstone regeneration project, in accordance with the details provided at Exempt Appendix A; and i) to add to the Clipstone Road Mansfield budget an additional revenue of £250,000 to allow for further development of the Phase 2 and 3 projects through to RIBA Stage 3. ...
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Meeting: 26 March 2024 Portfolio Holders: Councillor Paul Peacock, Strategy Performance & Finance Councillor Matthew Spoors, Sustainable Economic Development Director Lead: Matt Lamb – Director, Planning & Growth Sanjiv Kohli – Deputy Chief Executive & Director - Resources Lead Officer: Robert Ball – Major Capital Projects Delivery Manager (Corporate Property) Ellie Buchanan – Senior Regeneration Officer (Regeneration & Housing Strategy), Ext. 5238 Steven Adams – Senior Economic Regeneration Officer (Economic Growth & Visitor Economy), Ext. 5831

Report Summary

Type of Report Open Report (with exempt appendix), Key Decision

Report Title Sherwood Levelling Up 3 Update – Ollerton & Clipstone

To update Cabinet on the progress of the LUF 3 Programme, Purpose of Report including funding and details of the two place projects at Ollerton Town Centre and Mansfield Road, Clipstone That Cabinet:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sherwood Levelling Up 3 Update: Ollerton and Clipstone (Key Decision)Decisions 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 20 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, apologies
KM
Councillor Keith MeltonCommittee Member, present
EO
Councillor Emma OldhamCommittee Member, present
MS
Councillor Matthew SpoorsCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
RH
Councillor Rhona HollowayCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected

All 20 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Sherwood Levelling Up 3 Update - Ollerton and Clipstone (Key Decision)This decision
  2. Sherwood Levelling Up Fund (LUF) Programme Update (Key Decision)Approved
  3. Sherwood Levelling Up, Long Term Plan for Towns Fund and UKSPF / UKRPF Fund Update (Key Decision)Approved
  4. Sherwood Levelling Up 3 - Update 2 - Ollerton and Clipstone (Key Decision)Approved
  5. Sherwood Levelling Up Fund Update - Ollerton Town Centre and Mansfield Road, Clipstone (Key Decision)Agreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies