Resolved

That Cabinet approve: a) option 3 as set out in the report, to continue to carry out annual safety inspections and the required remedial maintenance, until the next Principal Bridge Inspection is due in 2030 at a cost of up to £XXXXXX; and b) the Capital budget be reduced from £333,500 to £XXXXXX which will decommit £XXXXXX from the Asset Maintenance Reserve. Reason for To ensure the bridge remains in a safe condition, the most viable option to the Council, based on the current condition of the bridge. Options Considered: Option 1 - Pay Commuted sum to Nottinghamshire County Council to have the bridge adopted and to remove future liability of the bridge from NSDC. Option 2 - To retain the bridge and to carry out a bridge major refurbishment. Option 3 - Continue to carry out annual safety inspections, remedial and recommended maintenance, until the next Principal Bridge Inspection is due, 2030. Option 4 - Close the bridge and decommission To ensure the bridge remains in a safe condition, the most viable option to the Council, based on the current condition of the bridge. Options Considered: Option 1 - Pay Commuted sum to Nottinghamshire County Council to have the bridge adopted and to remove future liability of the bridge from NSDC. Option 2 - To retain the bridge and to carry out a bridge major refurbishment. Option 3 - Continue to carry out annual safety inspections, remedial and recommended maintenance, until the next Principal Bridge Inspection is due, 2030. Option 4 - Close the bridge and decommission.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Background

1.1Previous reports have been presented to Members in February 2023 and March 2024.

2.0Details of Condition and Usage of the Bridge

2.1The bridge has recently been inspected by the Principal Bridge Inspector from VIA. VIA act for the Bridges and Structures Team Notts CC based at Trent Bridge House, Nottingham. The principal bridge inspection was completed on 11 June 2024.

2.2The principal bridge inspection stated that: ‘Structurally the bridge was in generally sound condition, with no significant defects in urgent need of repair’.

2.3The report also noted some minor maintenance/repairs are required and it gave the following recommendations. Items 1 to 3 have been carried out and are complete.

Item Location Defect Repairs required Timescale Estimated Traction East & West Loose Re-fix loose traction Within 3 £500 strips approach ramps traction strips months strips Surfacing Ends of main Deck Debris/leaf Removal Within 3 £250 (esp. east) mould months Timber West Approach Loose Re-fix boards Within 1 year £400 decking Ramp decking boards

Tie rods Support mast to Corrosion Remove corrosion Within 1 year £XXXX deck rods & apply protective paint system

Soffit East & West Green Cleaning of At bridge £4000 structural Approach ramps moss/mou Members ie owners members ld deposits pressure wash discretion (Aesthetic reasons only)

Upper Main span and Green Cleaning of At bridge £4000 structural support masts moss/mou members ie owners members ld deposits pressure wash discretion (Aesthetic reasons only) Parapet Entire structure Failed paint Maintenance Within 6 £2000 kick rails system/ painting years corrosion West West embankment Offensive Remove At bridge £500 Pier pier graffiti graffiti/treat with owner’s anti-graffiti discretion coating

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on Jubilee Bridge: Condition of Bridge and UsageReport 692 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 27 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, apologies
LB
Councillor Lee BrazierCommittee Member, present
SF
Councillor Simon FordeCommittee Member, apologies
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected
SK
Sanjiv KohliOfficer, expected

All 27 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Update on Jubilee Bridge - Condition of Bridge and UsageThis decision
  2. Update on Jubilee Bridge Maintenance Costs (Key Decision)Agreed
  3. Funding Requirement for Jubilee Bridge Maintenance Costs (Key Decision)Approved
  4. Jubilee Bridge - NewarkAgreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open